5969 W 75TH ST 90045
Certificate Information: 5969 W 75TH ST 90045
- Application / Permit
- 24014-10000-03868
- Plan Check / Job No.
- B24LA20448
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Remodel and addition to existing single-family dwelling; NFPA-13D fire sprinkler throughout
- Permit Issued
- Issued on 7/14/2025
- Issuing Office
- Current Status
- Issued on 7/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2024 | SINA KHOSRAVI |
| Corrections Issued | 8/31/2024 | SINA KHOSRAVI |
| Quality Review Completed | 9/11/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 9/30/2024 | SINA KHOSRAVI |
| Plan Check Approved | 10/24/2024 | SINA KHOSRAVI |
| Plan Check Approved | 6/12/2025 | INTERNET PERMIT |
| Issued | 7/14/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2024 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 9/4/2024 | DARIN LAM |
| Sewer availability | Cleared | 9/4/2024 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 10/2/2024 | JOSHUA JONES |
| GPI Written Notices | Cleared | 10/15/2024 | SINA KHOSRAVI |
| Grading Pre-Inspection | Cleared | 10/15/2024 | SINA KHOSRAVI |
Contact Information
| Architect | Hamilton,, John Patrick; Lic. No.: NA28865 | , |
| Contractor | Next Construction Inc; Lic. No.: 1049511-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: NA4978 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/17/2025 | Partial Inspection | JESUS PINEDA |
| Sewer | 8/20/2025 | Approved | RUBEN RIVAS |
| Underground Mechanical | 8/20/2025 | Partial Approval | RUBEN RIVAS |
| Footing/Foundation/Slab | 9/10/2025 | Corrections Issued | RUBEN RIVAS |
| Deputy Drilled-In Anchors | 9/11/2025 | Conditional Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 9/12/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 12/17/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 2/13/2026 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 2/13/2026 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 2/13/2026 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 2/19/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 2/19/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 2/19/2026 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 2/23/2026 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/4/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 3/4/2026 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/4/2026 | Approved | ANTHONY EGSON |
| Shower Pan | 3/4/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/11/2026 | Approved | JESUS PINEDA |
| Insulation | 3/12/2026 | Partial Approval | ANTHONY EGSON |
| Insulation | 3/16/2026 | Approved | BOBBY KEY |
| Drywall Nailing | 3/20/2026 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/20/2026 | Approved | ANTHONY EGSON |
| Gas Test | 5/5/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Gas Test | 5/20/2026 | Approved | MORRIS JACKSON |
| Service/Power Release | 5/20/2026 | Approved | MORRIS JACKSON |