215 N BRANCH ST 90042
Certificate Information: 215 N BRANCH ST 90042
- Application / Permit
- 24014-10000-03848
- Plan Check / Job No.
- B24LA20288
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 7'-6" X 10'-11" ADDITION TO THE EXISTING SINGLE FAMILY DWELLING - PER WFPP
- Permit Issued
- Issued on 4/7/2025
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 9/4/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 9/9/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 9/13/2024 | OMAR GARNICA |
| Issued | 4/7/2025 | APPLICANT |
| CofO in Progress | 9/3/2025 | DAVID WILLIAMS |
| Permit Finaled | 9/4/2025 | DEROLD HAUFF |
| Permit Finaled | 9/4/2025 | DEROLD HAUFF |
| CofO Issued | 9/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/4/2024 | DANIEL ABRAMYAN |
| Roof/Waste drainage to street | Cleared | 9/6/2024 | STEVEN JIN |
| Sewer availability | Cleared | 9/6/2024 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2024 | STEVEN JIN |
Contact Information
| Contractor | Ghukasyan Karen; Lic. No.: 861340-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/11/2025 | Approved | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 5/1/2025 | Conditional Approval | DAVID WILLIAMS |
| Wood Frame | 5/1/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Wood Frame | 5/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 5/29/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 5/29/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 5/29/2025 | Approved | DAVID WILLIAMS |
| Insulation | 6/2/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 6/9/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 6/9/2025 | Corrections Issued | DAVID WILLIAMS |
| Interior/Exterior Lathing | 6/11/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 6/27/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | DAVID WILLIAMS |
| Final | 8/29/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 8/29/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 8/29/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 9/2/2025 | Approved | DAVID WILLIAMS |
| Final | 9/2/2025 | OK to Issue CofO | DAVID WILLIAMS |