2313-2313 1/2 E ROGERS AVE 90023

Certificate Information: 2313-2313 1/2 E ROGERS AVE 90023

Application / Permit
24014-10000-03841
Plan Check / Job No.
B24LA20221
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT AN EXISTING SINGLE FAMILY DWELLING INTO A NEW DUPLEX WITH A FRONT AND REAR ADDITION
Permit Issued
Issued on 1/15/2025
Issuing Office
Metro
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2024 APPLICANT
Assigned to Plan Check Engineer 8/29/2024 HUAN LE
Corrections Issued 9/5/2024 SERGIO GUTIERREZ
Quality Review Completed 9/10/2024 KEN GILL
Building Plans Picked Up 9/18/2024 APPLICANT
Applicant returned to address corrections 10/28/2024 SERGIO GUTIERREZ
Applicant returned to address corrections 12/6/2024 SERGIO GUTIERREZ
Plan Check Approved 1/14/2025 HUAN LE
Issued 1/15/2025 APPLICANT
CofO in Progress 7/16/2025 FREDDIE RIVERA
Permit Finaled 7/16/2025 DEROLD HAUFF
CofO Issued 7/16/2025 DEROLD HAUFF
Permit Finaled 7/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/16/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 9/16/2024 JUSTIN BICOL
Permit Cleared 9/16/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 9/16/2024 JUSTIN BICOL
Sewer availability Cleared 9/16/2024 JUSTIN BICOL
Clean Up Green Up Cleared 10/29/2024 GEORGIA SMITH
Frnt yard landscape/Water mgmt Cleared 11/5/2024 GEORGIA SMITH
Hydrant and Access approval Cleared 12/19/2024 JERRY KAO
Grading Pre-Inspection Cleared 1/14/2025 SERGIO GUTIERREZ

Contact Information

Contractor So Cal Construction Enterprises Inc; Lic. No.: 832488-B P O BOX 96      SAN GABRIEL, CA 91778
Engineer Evangelista,, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/21/2025 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 1/21/2025 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Approved FREDDIE RIVERA
ELECTRICAL-Rough 2/28/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 2/28/2025 Approved FREDDIE RIVERA
HVAC-Rough 3/3/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/3/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 3/4/2025 Approved FREDDIE RIVERA
Green Building Rough 3/4/2025 Approved FREDDIE RIVERA
METHANE-Rough 3/4/2025 Approved FREDDIE RIVERA
Sewer 3/4/2025 Approved FREDDIE RIVERA
Insulation 3/7/2025 Approved ANTHONY RAMOS
Insulation 3/10/2025 Partial Inspection FREDDIE RIVERA
Drywall Nailing 3/12/2025 Approved FREDDIE RIVERA
Final 5/27/2025 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 5/27/2025 Partial Inspection FREDDIE RIVERA
Green Building Final 5/27/2025 Partial Inspection FREDDIE RIVERA
METHANE-Barrier 5/27/2025 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 5/27/2025 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/27/2025 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 5/27/2025 Partial Inspection FREDDIE RIVERA
Special/Order Compliance 5/27/2025 Partial Inspection OSVALDO PARAMO
Verify Rec and Parks Fee Memo 6/17/2025 Approved FREDDIE RIVERA
Final 7/1/2025 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 7/1/2025 Approved OSVALDO PARAMO
Green Building Final 7/1/2025 Approved OSVALDO PARAMO
METHANE-Barrier 7/1/2025 Approved OSVALDO PARAMO
METHANE-Subgrade 7/1/2025 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Approved OSVALDO PARAMO
Service/Power Release 7/1/2025 Approved OSVALDO PARAMO
Smoke Detectors 7/1/2025 Approved OSVALDO PARAMO
Final 7/7/2025 OK to Issue CofO FREDDIE RIVERA