7401 S OGELSBY AVE 90045

Certificate Information: 7401 S OGELSBY AVE 90045

Application / Permit
24014-10000-03833
Plan Check / Job No.
B24LA20156
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN REMODEL EXISTING SINGLE-FAMILY DWELLING WITH ADDITION
Permit Issued
Issued on 5/23/2025
Issuing Office
Current Status
CofO in Progress on 1/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/28/2024 APPLICANT
Assigned to Plan Check Engineer 9/3/2024 ALEC MOUSAKHANIAN
Corrections Issued 9/4/2024 ALEC MOUSAKHANIAN
Applicant returned to address corrections 4/14/2025 ALEC MOUSAKHANIAN
Plan Check Approved 4/29/2025 ALEC MOUSAKHANIAN
Issued 5/23/2025 APPLICANT
CofO in Progress 12/18/2025 ANTHONY EGSON
No Progress 1/2/2026 ANTHONY EGSON
CofO in Progress 1/2/2026 ANTHONY EGSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/19/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/19/2025 LEE GUILBEAUX
Sewer availability Cleared 3/19/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/19/2025 LEE GUILBEAUX
Grading Pre-Inspection Cleared 4/10/2025 LANNY MERRICK
Specific Plan Cleared 4/25/2025 EDER ROMERO
GPI Written Notices Cleared 4/29/2025 ALEC MOUSAKHANIAN

Contact Information

Contractor Ofir Construction Inc; Lic. No.: 1036242-B       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/21/2025 Approved RUBEN RIVAS
METHANE-Barrier 7/21/2025 Partial Approval RUBEN RIVAS
METHANE-Subgrade 7/21/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 8/15/2025 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 8/15/2025 Approved RUBEN RIVAS
Green Building Rough 8/15/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 8/15/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 8/15/2025 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Rough 8/19/2025 Approved RUBEN RIVAS
Insulation 8/22/2025 Approved RUBEN RIVAS
Drywall Nailing 8/25/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 8/25/2025 Approved RUBEN RIVAS
Shower Pan 8/27/2025 No Access for Inspection RUBEN RIVAS
Shower Pan 9/3/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 11/14/2025 Approved RUBEN RIVAS
Final 11/14/2025 Corrections Issued RUBEN RIVAS
Green Building Final 11/14/2025 Approved RUBEN RIVAS
Green Building Rough 11/14/2025 Approved RUBEN RIVAS
MERV13>=Rough 11/14/2025 Approved RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Approved RUBEN RIVAS
Smoke Detectors 11/14/2025 Approved RUBEN RIVAS
Final 11/26/2025 No Access for Inspection ANTHONY EGSON
Final 12/4/2025 Corrections Issued ANTHONY EGSON
Final 12/17/2025 OK to Issue CofO ANTHONY EGSON