5310 S VICTORIA AVE 90043
Certificate Information: 5310 S VICTORIA AVE 90043
- Application / Permit
- 24014-10000-03825
- Plan Check / Job No.
- B24LA20069
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Addition to and Conversion of (E) Detached Garage to Accessory Dwelling Unit per Ordinance .
- Permit Issued
- Issued on 1/7/2025
- Issuing Office
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2024 | KELVIN CHUONG |
| Corrections Issued | 8/31/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 9/16/2024 | GEORGE ALVAREZ |
| Plan Check Approved | 1/7/2025 | SAMUEL GONZALEZ |
| Issued | 1/7/2025 | APPLICANT |
| CofO in Progress | 11/19/2025 | LUIS CASTRO |
| Permit Finaled | 11/21/2025 | DEROLD HAUFF |
| CofO Issued | 11/21/2025 | DEROLD HAUFF |
| Permit Finaled | 11/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 9/6/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 9/9/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 12/26/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Maestro Construction Inc; Lic. No.: 1060987-B | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/9/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 4/9/2025 | Partial Approval | LUIS CASTRO |
| Sewer | 4/9/2025 | Conditional Approval | LUIS CASTRO |
| Deputy Drilled-In Anchors | 4/15/2025 | Approved | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 4/15/2025 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 4/15/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 5/28/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 5/28/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 5/28/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/29/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 5/29/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 5/29/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 5/29/2025 | Partial Approval | LUIS CASTRO |
| Underground Mechanical | 5/29/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 6/13/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2025 | Approved | LUIS CASTRO |
| Insulation | 6/13/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 6/18/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 6/30/2025 | Approved | LUIS CASTRO |
| Shower Pan | 6/30/2025 | Approved | LUIS CASTRO |
| Final | 10/23/2025 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 10/23/2025 | Approved | LUIS CASTRO |
| Green Building Final | 10/23/2025 | Not Ready for Inspection | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Not Required | LUIS CASTRO |
| Smoke Detectors | 10/23/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 10/29/2025 | Approved | LUIS CASTRO |
| Final | 10/29/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 10/29/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 10/29/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 10/29/2025 | Approved | LUIS CASTRO |
| Final | 11/18/2025 | OK to Issue CofO | LUIS CASTRO |