7221 W SUMMITROSE ST 91042

Certificate Information: 7221 W SUMMITROSE ST 91042

Application / Permit
24014-10000-03805
Plan Check / Job No.
B24LA19892
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER CA GOVT CODE 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) . ALL ELECTRIC BUILDING . WORK PER ENGINEERED DESIGN .
Permit Issued
Issued on 2/4/2025
Issuing Office
Metro
Current Status
CofO Issued on 6/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2024 APPLICANT
Assigned to Plan Check Engineer 8/29/2024 NEHEMIAS RAMOS
Corrections Issued 8/31/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 1/21/2025 NEHEMIAS RAMOS
Plan Check Approved 1/23/2025 GEORGE ALVAREZ
Issued 2/4/2025 APPLICANT
CofO in Progress 4/24/2026 NICHOLAS TROWBRIDGE
CofO Issued 6/2/2026 RUBEN SALAS
Permit Finaled 6/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/30/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 12/30/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/2/2025 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 1/17/2025 MANUEL TEJADA
Sewer availability Cleared 1/23/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2025 Approved DAVID ANDERSON
PLUMBING-Rough 3/21/2025 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 3/26/2025 Approved WILLIAM WREN
Deputy Wood Construction 4/10/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 5/28/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 5/28/2025 Approved WILLIAM WREN
Green Building Rough 5/28/2025 Approved WILLIAM WREN
HVAC-Rough 5/28/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 5/28/2025 Approved WILLIAM WREN
PLUMBING-Rough 5/28/2025 Approved WILLIAM WREN
Verify Sprinkler Sign Off 5/28/2025 Approved WILLIAM WREN
Insulation 6/6/2025 Approved JOAQUIN GREENOUGH
Drywall Nailing 6/12/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 6/25/2025 Approved WILLIAM WREN
Shower Pan 6/25/2025 Approved WILLIAM WREN
Sewer 12/3/2025 Approved NICHOLAS TROWBRIDGE
Final 2/5/2026 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 2/5/2026 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Not Required NICHOLAS TROWBRIDGE
Service/Power Release 2/5/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 2/5/2026 Approved NICHOLAS TROWBRIDGE
Final 3/31/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Service/Power Release 3/31/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 4/9/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Service/Power Release 4/9/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 4/13/2026 OK to Issue CofO NICHOLAS TROWBRIDGE
Service/Power Release 4/13/2026 Approved NICHOLAS TROWBRIDGE