2810 S SELBY AVE 90064
Certificate Information: 2810 S SELBY AVE 90064
- Application / Permit
- 24014-10000-03803
- Plan Check / Job No.
- B24LA19877
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: SFD House Interior Remodel & Addition to SFD
- Permit Issued
- Issued on 12/23/2024
- Issuing Office
- Current Status
- Issued on 12/23/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 9/4/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 10/9/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 10/15/2024 | NEHEMIAS RAMOS |
| Issued | 12/23/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2024 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 9/27/2024 | MICHAEL TEMPLE |
| Specific Plan | Cleared | 9/30/2024 | KYLE WINSTON |
| Specific Plan | Cleared | 10/1/2024 | RICHARD WOO |
| Roof/Waste drainage to street | Cleared | 10/2/2024 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Alsa Construction; Lic. No.: 1098988-B | , |
| Engineer | Wu,, Shu; Lic. No.: NA90391 | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/21/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 2/4/2025 | No Access for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 2/10/2025 | Not Ready for Inspection | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Approved | WILBER ROSALES |
| Special/Order Compliance | 3/10/2025 | Partial Inspection | BOBBY KEY |
| Pre-Inspection | 3/21/2025 | Corrections Issued | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 4/24/2025 | No Access for Inspection | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 4/30/2025 | Corrections Issued | ARAM AVEDISIAN |
| Wood Frame | 5/15/2025 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Partial Approval | DANIEL VERA |
| HVAC-Rough | 5/20/2025 | Not Ready for Inspection | DANIEL VERA |
| Rough-Elec/Plmb/HVAC | 5/20/2025 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 5/27/2025 | Not Ready for Inspection | BOBBY KEY |
| Green Building Rough | 5/27/2025 | Corrections Issued | BOBBY KEY |
| MERV13>=Rough | 5/27/2025 | Corrections Issued | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 5/27/2025 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 6/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 6/3/2025 | Conditional Approval | STEPHANIE SWANSON |
| HVAC-Rough | 6/5/2025 | Corrections Issued | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 6/13/2025 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 6/13/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Insulation | 7/1/2025 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/5/2025 | Corrections Issued | KIRK SANDERS |
| Drywall Nailing | 8/5/2025 | Conditional Approval | KIRK SANDERS |
| HVAC-Rough | 8/5/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 9/9/2025 | Approved | ASHLEY THOMPSON |
| Shower Pan | 9/9/2025 | Approved | ASHLEY THOMPSON |
| Pre-Inspection | 2/20/2026 | Partial Inspection | DANIEL VERA |