1558 W AVERILL PARK DR 90732
Certificate Information: 1558 W AVERILL PARK DR 90732
- Application / Permit
- 24014-10000-03784
- Plan Check / Job No.
- B24LA19696
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN ADDITION OF AN ADU AT A SECOND STORY TO AN (E) ONE STORY DETACHED GARAGE PER STATE LAW
- Permit Issued
- Issued on 3/5/2025
- Issuing Office
- Current Status
- Issued on 3/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | KHUONG TRUONG |
| Corrections Issued | 9/9/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/10/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/7/2025 | KHUONG TRUONG |
| Applicant returned to address corrections | 1/14/2025 | KHUONG TRUONG |
| Plan Check Approved | 1/16/2025 | KHUONG TRUONG |
| Issued | 3/5/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2024 | ERIK BEASLEY |
| Street Frontage | Cleared | 10/8/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2024 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 10/9/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/9/2024 | ERIK BEASLEY |
| GPI Written Notices | Cleared | 1/14/2025 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 1/14/2025 | SERGIO GUTIERREZ |
Contact Information
| Architect | Guirgis,, Nevert R; Lic. No.: C34119 | 6034 MOSSBANK DRIVE RANCHO PALOS VERDES, CA 90275 |
| Contractor | Kma Inspection And Construction Services; Lic. No.: 1024938-B | 8215 E WHITE OAK RIDGE #99 ORANGE, CA 92869 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/6/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/6/2025 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 3/6/2025 | Corrections Issued | JOSEPH MCGARRY |
| Underground Mechanical | 3/6/2025 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/28/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Pre-Inspection | 3/28/2025 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/3/2025 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/15/2025 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/25/2025 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 5/5/2025 | Partial Approval | JOSEPH MCGARRY |
| Deputy Other (see comments) | 5/5/2025 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 5/12/2025 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 6/16/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/16/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Deputy Wood Construction | 6/23/2025 | No Access for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 7/31/2025 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/31/2025 | Approved | JOSEPH MCGARRY |
| Shower Pan | 7/31/2025 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/5/2025 | No Access for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 8/5/2025 | No Access for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/7/2025 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 8/7/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/12/2025 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 8/12/2025 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/12/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/10/2025 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/10/2025 | Partial Inspection | JOSEPH MCGARRY |
| Green Building Rough | 9/10/2025 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 9/10/2025 | Approved | JOSEPH MCGARRY |
| Insulation | 9/12/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 9/24/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/18/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/16/2026 | No Access for Inspection | JOSEPH MCGARRY |
| Final | 4/16/2026 | No Access for Inspection | JOSEPH MCGARRY |
| Green Building Final | 4/16/2026 | No Access for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/16/2026 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 4/16/2026 | No Access for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/28/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 4/28/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 4/28/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Final | 4/28/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 4/28/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/29/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 4/29/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Final | 4/29/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/29/2026 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 4/29/2026 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/16/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 6/16/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 6/16/2026 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 6/18/2026 | Corrections Issued | JOSEPH MCGARRY |
| Final | 6/18/2026 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 6/18/2026 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 6/18/2026 | Corrections Issued | JOSEPH MCGARRY |