4168 S KENYON AVE 90066

Certificate Information: 4168 S KENYON AVE 90066

Application / Permit
24014-10000-03755
Plan Check / Job No.
B24LA19471
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Major interior remodel and addition to existing 1-story single family dwelling; reconfigure layout, conversion of existing garage into habitable area, add new 2-car garage w/ storage mezzanine.
Permit Issued
Issued on 4/15/2025
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2024 APPLICANT
Assigned to Plan Check Engineer 8/28/2024 CAROLEAN BASMA
Corrections Issued 8/28/2024 CAROLEAN BASMA
Plan Check Approved 11/6/2024 CAROLEAN BASMA
Issued 4/15/2025 APPLICANT
CofO in Progress 12/29/2025 ANTHONY EGSON
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 9/10/2024 RICHARD WOO
Eng Process Fee Ord 176,300 Cleared 10/9/2024 BRENDEN HAWK
Sewer availability Cleared 10/9/2024 BRENDEN HAWK
Roof/Waste drainage to street Cleared 10/25/2024 DARIN LAM

Contact Information

Contractor Projekta Inc; Lic. No.: 1010761-B       ,
Engineer Le,, Thang Huu; Lic. No.: NA4978       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/14/2025 Corrections Issued RUBEN RIVAS
Footing/Foundation/Slab 5/14/2025 Corrections Issued RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 5/16/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Corrections Issued RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 8/13/2025 Corrections Issued RUBEN RIVAS
Footing/Foundation/Slab 8/13/2025 Approved RUBEN RIVAS
Green Building Rough 8/13/2025 Not Ready for Inspection RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 9/29/2025 No Access for Inspection RUBEN RIVAS
ELECTRICAL-Rough 9/29/2025 No Access for Inspection RUBEN RIVAS
Green Building Rough 9/29/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 9/29/2025 No Access for Inspection RUBEN RIVAS
Interior/Exterior Lathing 9/29/2025 No Access for Inspection RUBEN RIVAS
PLUMBING-Rough 9/29/2025 No Access for Inspection RUBEN RIVAS
ELECTRICAL-Rough 10/1/2025 Approved RUBEN RIVAS
HVAC-Rough 10/1/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 10/1/2025 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Rough 10/1/2025 Partial Approval RUBEN RIVAS
Insulation 10/3/2025 Approved RUBEN RIVAS
Drywall Nailing 10/10/2025 Approved RUBEN RIVAS
Green Building Rough 10/10/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 10/20/2025 Approved RUBEN RIVAS
Shower Pan 10/20/2025 Approved RUBEN RIVAS
Gas Test 12/3/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 12/11/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 12/11/2025 Approved ANTHONY EGSON
Final 12/11/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Final 12/11/2025 Approved ANTHONY EGSON
HVAC-Final 12/11/2025 Approved ANTHONY EGSON
PLUMBING-Final 12/11/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Approved ANTHONY EGSON
Smoke Detectors 12/11/2025 Approved ANTHONY EGSON
Final 12/24/2025 Conditional Approval ANTHONY EGSON
Deputy Wood Construction 12/26/2025 Conditional Approval ANTHONY EGSON
Final 12/26/2025 OK to Issue CofO ANTHONY EGSON