4168 S KENYON AVE 90066
Certificate Information: 4168 S KENYON AVE 90066
- Application / Permit
- 24014-10000-03755
- Plan Check / Job No.
- B24LA19471
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Major interior remodel and addition to existing 1-story single family dwelling; reconfigure layout, conversion of existing garage into habitable area, add new 2-car garage w/ storage mezzanine.
- Permit Issued
- Issued on 4/15/2025
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2024 | CAROLEAN BASMA |
| Corrections Issued | 8/28/2024 | CAROLEAN BASMA |
| Plan Check Approved | 11/6/2024 | CAROLEAN BASMA |
| Issued | 4/15/2025 | APPLICANT |
| CofO in Progress | 12/29/2025 | ANTHONY EGSON |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/10/2024 | RICHARD WOO |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2024 | BRENDEN HAWK |
| Sewer availability | Cleared | 10/9/2024 | BRENDEN HAWK |
| Roof/Waste drainage to street | Cleared | 10/25/2024 | DARIN LAM |
Contact Information
| Contractor | Projekta Inc; Lic. No.: 1010761-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: NA4978 | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/14/2025 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 5/14/2025 | Corrections Issued | RUBEN RIVAS |
| Excavation/Setback/Form/Re-Bar | 5/16/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Corrections Issued | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 8/13/2025 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 8/13/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 8/13/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 9/29/2025 | No Access for Inspection | RUBEN RIVAS |
| ELECTRICAL-Rough | 9/29/2025 | No Access for Inspection | RUBEN RIVAS |
| Green Building Rough | 9/29/2025 | Not Ready for Inspection | RUBEN RIVAS |
| HVAC-Rough | 9/29/2025 | No Access for Inspection | RUBEN RIVAS |
| Interior/Exterior Lathing | 9/29/2025 | No Access for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 9/29/2025 | No Access for Inspection | RUBEN RIVAS |
| ELECTRICAL-Rough | 10/1/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 10/1/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 10/1/2025 | Not Ready for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 10/1/2025 | Partial Approval | RUBEN RIVAS |
| Insulation | 10/3/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 10/10/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 10/10/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 10/20/2025 | Approved | RUBEN RIVAS |
| Shower Pan | 10/20/2025 | Approved | RUBEN RIVAS |
| Gas Test | 12/3/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/11/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/11/2025 | Approved | ANTHONY EGSON |
| Final | 12/11/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 12/11/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 12/11/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 12/11/2025 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/11/2025 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 12/11/2025 | Approved | ANTHONY EGSON |
| Final | 12/24/2025 | Conditional Approval | ANTHONY EGSON |
| Deputy Wood Construction | 12/26/2025 | Conditional Approval | ANTHONY EGSON |
| Final | 12/26/2025 | OK to Issue CofO | ANTHONY EGSON |