1538 S REXFORD DR 90035
Certificate Information: 1538 S REXFORD DR 90035
- Application / Permit
- 24014-10000-03749
- Plan Check / Job No.
- B24LA19445
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) Detached garage to Accessory Dwelling Unit with addition per LAMC 12.22 A.33 (c)-(d). Design per licensed engineer.
- Permit Issued
- Issued on 7/3/2025
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2024 | CAROLEAN BASMA |
| Corrections Issued | 8/30/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 12/23/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 1/7/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 1/16/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 1/30/2025 | DAVID CASTILLO |
| Plan Check Approved | 2/4/2025 | DAVID CASTILLO |
| Issued | 7/3/2025 | APPLICANT |
| CofO in Progress | 4/1/2026 | ASHLEY THOMPSON |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
| CofO Issued | 4/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 9/13/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 9/19/2024 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 9/23/2024 | VASIL MIHALEV |
| Construction near power lines | Cleared | 12/18/2024 | RIDWAN HARDY |
Contact Information
| Architect | Suayan,, Rey D; Lic. No.: NA37726 | , |
| Contractor | Rent Ready Construction Inc; Lic. No.: 1065376-B | , |
| Engineer | Brown,, Patrick John; Lic. No.: C45526 | 7 STARLING LAGUNA BEACH, CA 92656 |
| Engineer | Mourad,, Daniel; Lic. No.: NA83387 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/1/2025 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 8/12/2025 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 8/12/2025 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 8/12/2025 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 9/3/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Barrier | 9/3/2025 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 10/16/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 10/16/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 10/21/2025 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Rough | 10/21/2025 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Wood Construction | 10/22/2025 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 10/27/2025 | Approved | EVAN COOPER |
| Green Building Rough | 10/27/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 10/27/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 10/27/2025 | Partial Approval | EVAN COOPER |
| METHANE-Rough | 10/27/2025 | Approved | EVAN COOPER |
| Insulation | 10/31/2025 | Conditional Approval | ASHLEY THOMPSON |
| Drywall Nailing | 11/10/2025 | Conditional Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/10/2025 | Approved | ASHLEY THOMPSON |
| Underground Mechanical | 11/10/2025 | Corrections Issued | ASHLEY THOMPSON |
| Underground Mechanical | 12/18/2025 | Partial Approval | EVAN COOPER |
| Underground Mechanical | 1/6/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Underground Mechanical | 1/7/2026 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/19/2026 | Corrections Issued | ASHLEY THOMPSON |
| Final | 3/19/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 3/19/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 3/19/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 3/19/2026 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Not Required | ASHLEY THOMPSON |
| Service/Power Release | 3/19/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 3/19/2026 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/27/2026 | Approved | ASHLEY THOMPSON |
| Final | 3/27/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| PLUMBING-Final | 3/27/2026 | Approved | ASHLEY THOMPSON |