3307 3/4 E 3RD ST 90063
Certificate Information: 3307 3/4 E 3RD ST 90063
- Application / Permit
- 24014-10000-03744
- Plan Check / Job No.
- B24LA19388
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERT EXISTING GARAGE WITH ADDITION INTO NEW DETACHED ADU, WORK PER WFPP.
- Permit Issued
- Issued on 7/27/2025
- Issuing Office
- Current Status
- Issued on 7/27/2025
Permit Application Status History
| Submitted | 8/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 8/27/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 10/23/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 11/21/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 12/3/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 12/6/2024 | FERNANDO FLORES |
| Plan Check Approved | 2/7/2025 | CARLOS MONTES |
| Issued | 7/27/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/5/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 10/22/2024 | DAVID LOPEZ |
| Grading Pre-Inspection | Cleared | 12/3/2024 | LANNY MERRICK |
| Address approval | Cleared | 12/5/2024 | DAVID LOPEZ |
| Clean Up Green Up | Cleared | 12/24/2024 | RUBEN VASQUEZ |
| Construction near power lines | Cleared | 2/4/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History