4912 S CIMARRON ST 90062

Certificate Information: 4912 S CIMARRON ST 90062

Application / Permit
24014-10000-03730
Plan Check / Job No.
B24LA19238
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
TWO STORY ADDTION TO GARAGE FOR NEW ADU.
Permit Issued
Issued on 2/27/2025
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 JOE VO
Corrections Issued 9/16/2024 JOE VO
Quality Review Completed 9/17/2024 GARO TELMI
Applicant returned to address corrections 11/21/2024 JOE VO
Plan Check Approved 2/18/2025 JOE VO
Issued 2/27/2025 APPLICANT
CofO in Progress 11/18/2025 SABAS ALONSO
Permit Finaled 11/18/2025 DEROLD HAUFF
CofO Issued 11/18/2025 DEROLD HAUFF
Permit Finaled 11/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/9/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 10/9/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 10/15/2024 DAVID LOPEZ
Sewer availability Cleared 10/15/2024 DAVID LOPEZ
Construction near power lines Cleared 11/8/2024 RIDWAN HARDY
Hydrant and Access approval Cleared 2/10/2025 JERRY KAO
Hold Cleared 3/14/2025 ALEXIS SCHULTZ

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/11/2025 Approved SABAS ALONSO
Underground Mechanical 3/11/2025 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 3/18/2025 Corrections Issued WILLIAM SIERRA
Excavation/Setback/Form/Re-Bar 3/21/2025 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 4/2/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 4/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/27/2025 Corrections Issued BARRY HACHE
Underground Mechanical 5/27/2025 Approved BARRY HACHE
ELECTRICAL-Rough 5/29/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Approved LUIS CASTRO
HVAC-Rough 5/29/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 5/29/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 6/26/2025 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 6/26/2025 Approved SABAS ALONSO
Green Building Rough 6/26/2025 Approved SABAS ALONSO
HVAC-Rough 6/26/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 6/26/2025 Partial Approval SABAS ALONSO
Shower Pan 6/26/2025 Partial Approval SABAS ALONSO
Insulation 7/18/2025 Conditional Approval RONNIE MEDINA
Interior/Exterior Lathing 7/18/2025 Approved RONNIE MEDINA
Shower Pan 7/18/2025 Approved RONNIE MEDINA
Drywall Nailing 7/30/2025 Approved ANTHONY RAMOS
Insulation 7/30/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 11/3/2025 Approved SABAS ALONSO
ELECTRICAL-Final 11/3/2025 Approved SABAS ALONSO
Final 11/3/2025 Corrections Issued SABAS ALONSO
Green Building Final 11/3/2025 Approved SABAS ALONSO
HVAC-Final 11/3/2025 Approved SABAS ALONSO
PLUMBING-Final 11/3/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 11/3/2025 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 11/3/2025 Approved SABAS ALONSO
Final 11/17/2025 OK to Issue CofO SABAS ALONSO
Service/Power Release 11/17/2025 Approved SABAS ALONSO