1114 W 46TH ST 90037

Certificate Information: 1114 W 46TH ST 90037

Application / Permit
24014-10000-03721
Plan Check / Job No.
B24LA19156
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF NEW ADU TO (E) DETACHED GARAGE PER LAMC 12.22 A.33 (c)-(d) WITH PATIO COVER & RETROFIT GARAGE Approved per Case No. ADM-2024-5502-ADU-CPIOC
Permit Issued
Issued on 1/14/2025
Issuing Office
Metro
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 MINA HABILI
Corrections Issued 8/24/2024 MINA HABILI
Building Plans Picked Up 8/27/2024 APPLICANT
Plan Check Approved 9/9/2024 JOSE VELAZQUEZ
Issued 1/14/2025 APPLICANT
CofO in Progress 3/23/2026 BARRY HACHE
CofO Issued 3/26/2026 DEROLD HAUFF
Permit Finaled 3/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/26/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/29/2024 JESSICA OPINION
Sewer availability Cleared 8/29/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 9/3/2024 TREVOR QUAN
Community Plan Implem. Overlay Cleared 9/4/2024 MANERI ROMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo Andres; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/1/2025 Approved BARRY HACHE
PLUMBING-Rough 7/10/2025 Approved BARRY HACHE
Deputy Drilled-In Anchors 7/18/2025 Conditional Approval BARRY HACHE
Excavation/Setback/Form/Re-Bar 7/18/2025 Approved BARRY HACHE
Footing/Foundation/Slab 7/18/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Corrections Issued BARRY HACHE
Underground Mechanical 9/25/2025 Approved BARRY HACHE
ELECTRICAL-Rough 9/29/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 9/29/2025 Approved BARRY HACHE
HVAC-Rough 9/29/2025 Approved BARRY HACHE
PLUMBING-Rough 9/29/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 11/13/2025 Not Ready for Inspection BARRY HACHE
Interior/Exterior Lathing 11/13/2025 Partial Approval BARRY HACHE
PLUMBING-Rough 11/13/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 11/18/2025 Corrections Issued BARRY HACHE
Green Building Rough 11/18/2025 Approved BARRY HACHE
Rough-Elec/Plmb/HVAC 11/18/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 12/5/2025 Approved BARRY HACHE
Insulation 12/9/2025 Approved ALEX COLIN
Drywall Nailing 12/17/2025 Approved ALEX COLIN
Shower Pan 12/17/2025 Approved ALEX COLIN
Interior/Exterior Lathing 1/12/2026 No Access for Inspection BARRY HACHE
Interior/Exterior Lathing 1/13/2026 Approved BARRY HACHE
Green Building Final 3/11/2026 Not Ready for Inspection BARRY HACHE
HVAC-Final 3/11/2026 Corrections Issued BARRY HACHE
PLUMBING-Final 3/11/2026 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 3/11/2026 SGSOV Not Ready BARRY HACHE
ELECTRICAL-Final 3/18/2026 Corrections Issued BARRY HACHE
Final 3/18/2026 Not Ready for Inspection BARRY HACHE
Green Building Final 3/18/2026 Approved BARRY HACHE
HVAC-Final 3/18/2026 Approved BARRY HACHE
PLUMBING-Final 3/18/2026 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 3/18/2026 SGSOV Approved BARRY HACHE
Smoke Detectors 3/18/2026 Corrections Issued BARRY HACHE
ELECTRICAL-Final 3/23/2026 Approved BARRY HACHE
Final 3/23/2026 OK to Issue CofO BARRY HACHE
Smoke Detectors 3/23/2026 Approved BARRY HACHE