1826 W 51ST ST 90062
Certificate Information: 1826 W 51ST ST 90062
- Application / Permit
- 24014-10000-03704
- Plan Check / Job No.
- B24LA18987
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. (N) One Story Detached ADU (27ft x 21ft) .
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2024 | TSE MING HUANG |
| Corrections Issued | 1/3/2025 | TSE MING HUANG |
| Applicant returned to address corrections | 1/15/2025 | ALEXANDER JOO |
| Plan Check Approved | 1/16/2025 | TSE MING HUANG |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 7/29/2025 | SABAS ALONSO |
| Permit Finaled | 7/31/2025 | DEROLD HAUFF |
| Permit Finaled | 7/31/2025 | DEROLD HAUFF |
| CofO Issued | 7/31/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/4/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 9/4/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 9/10/2024 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 11/25/2024 | JERRY KAO |
| Construction near power lines | Cleared | 12/4/2024 | TINA MIRANDA |
| Construction within easement | Cleared | 12/4/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/3/2025 | Partial Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 3/10/2025 | Corrections Issued | SABAS ALONSO |
| Deputy Drilled-In Anchors | 3/12/2025 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/14/2025 | Approved | SABAS ALONSO |
| Sewer | 3/24/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/24/2025 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 4/4/2025 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 4/4/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 4/10/2025 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 4/23/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 4/23/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 4/30/2025 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 4/30/2025 | Corrections Issued | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/2/2025 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 5/2/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 5/2/2025 | Approved | SABAS ALONSO |
| Insulation | 5/6/2025 | Corrections Issued | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 5/12/2025 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 5/12/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Approved | SABAS ALONSO |
| Insulation | 5/14/2025 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/22/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/22/2025 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 5/22/2025 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 5/27/2025 | Approved | ANTHONY RAMOS |
| Final | 6/18/2025 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 6/18/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 6/18/2025 | Approved | SABAS ALONSO |
| Final | 7/28/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 7/28/2025 | Not Ready for Inspection | SABAS ALONSO |