1826 W 51ST ST 90062

Certificate Information: 1826 W 51ST ST 90062

Application / Permit
24014-10000-03704
Plan Check / Job No.
B24LA18987
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. (N) One Story Detached ADU (27ft x 21ft) .
Permit Issued
Issued on 1/17/2025
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2024 APPLICANT
Assigned to Plan Check Engineer 8/26/2024 TSE MING HUANG
Corrections Issued 1/3/2025 TSE MING HUANG
Applicant returned to address corrections 1/15/2025 ALEXANDER JOO
Plan Check Approved 1/16/2025 TSE MING HUANG
Issued 1/17/2025 APPLICANT
CofO in Progress 7/29/2025 SABAS ALONSO
Permit Finaled 7/31/2025 DEROLD HAUFF
Permit Finaled 7/31/2025 DEROLD HAUFF
CofO Issued 7/31/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/4/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 9/4/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/10/2024 DAVID LOPEZ
Sewer availability Cleared 9/10/2024 DAVID LOPEZ
Hydrant and Access approval Cleared 11/25/2024 JERRY KAO
Construction near power lines Cleared 12/4/2024 TINA MIRANDA
Construction within easement Cleared 12/4/2024 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Acciani,, Mark; Lic. No.: C83929 PO BOX 1390      RUNNING SPRINGS, CA 92382

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/3/2025 Partial Inspection SABAS ALONSO
Footing/Foundation/Slab 3/10/2025 Corrections Issued SABAS ALONSO
Deputy Drilled-In Anchors 3/12/2025 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 3/14/2025 Approved SABAS ALONSO
Sewer 3/24/2025 Approved SABAS ALONSO
Underground Mechanical 3/24/2025 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 4/4/2025 Partial Approval SABAS ALONSO
PLUMBING-Rough 4/4/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 4/10/2025 No Access for Inspection SABAS ALONSO
ELECTRICAL-Rough 4/23/2025 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 4/23/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 4/30/2025 Corrections Issued MICHAEL LEWIS
HVAC-Rough 4/30/2025 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 5/2/2025 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 5/2/2025 Approved SABAS ALONSO
Green Building Rough 5/2/2025 Approved SABAS ALONSO
Insulation 5/6/2025 Corrections Issued ANTHONY RAMOS
BUILDING-Rough-Frame 5/12/2025 Approved SABAS ALONSO
Verify Sprinkler Sign Off 5/12/2025 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Approved SABAS ALONSO
Insulation 5/14/2025 Approved SABAS ALONSO
Drywall Nailing 5/22/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 5/22/2025 Not Ready for Inspection SABAS ALONSO
Shower Pan 5/22/2025 Not Ready for Inspection SABAS ALONSO
Shower Pan 5/27/2025 Approved ANTHONY RAMOS
Final 6/18/2025 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/18/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 6/18/2025 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 6/18/2025 Approved SABAS ALONSO
Final 7/28/2025 OK to Issue CofO SABAS ALONSO
Service/Power Release 7/28/2025 Not Ready for Inspection SABAS ALONSO