10693 W CHALON ROAD 90077
Certificate Information: 10693 W CHALON ROAD 90077
- Application / Permit
- 24014-10000-03701
- Plan Check / Job No.
- B24LA18982
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan, First- and second-floor addition, new carport, and major remodel to the existing two-story single-family dwelling with attached garage. NFPA 13D system provided. (Portion of north corner wall and foundation to remain; see comments "COMPLY WITH DEPARTMENT ORDER effective date 02/04/2013.
- Permit Issued
- Issued on 9/19/2025
- Issuing Office
- Current Status
- Issued on 9/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | SAM CHANG |
| Corrections Issued | 9/17/2024 | KESETE HAREGOT |
| Quality Review Completed | 9/17/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/14/2025 | KESETE HAREGOT |
| Applicant returned to address corrections | 2/28/2025 | KESETE HAREGOT |
| Applicant returned to address corrections | 7/24/2025 | SAM CHANG |
| Applicant returned to address corrections | 7/30/2025 | SAM CHANG |
| Plan Check Approved | 9/3/2025 | KESETE HAREGOT |
| Plan Check Approved | 9/19/2025 | MICHAEL PEREZ |
| Issued | 9/19/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/5/2024 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 9/5/2024 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 9/5/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2024 | LIAM ODONOVAN |
| Address approval | Cleared | 2/4/2025 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 2/4/2025 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/13/2025 | PATRICK PEREZ |
| Miscellaneous | Cleared | 3/14/2025 | DIANA RENTERIA |
| Disturb/Remove Protected Trees | Cleared | 5/14/2025 | MIGUEL ORNELAS |
| Low Impact Development (LID) | Cleared | 7/23/2025 | ERNEST TSE |
| GPI Written Notices | Cleared | 7/24/2025 | KESETE HAREGOT |
| Grading Pre-Inspection | Cleared | 7/24/2025 | KESETE HAREGOT |
| Green Code | Cleared | 7/24/2025 | KESETE HAREGOT |
Contact Information
| Architect | Pedroso,, Gonzalo J; Lic. No.: NA26455 | , |
| Contractor | Valle/Reinis Builders Inc; Lic. No.: 839178-B | , |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Ekmekji,, Steve Eli; Lic. No.: C66727 | 19281 BERCLAIR LANE TARZANA, CA 91356 |
| Engineer | Liston,, Leonard Irvin; Lic. No.: C93123 | 889 PIERCE COURT, SUITE 101 THOUSAND OAKS, CA 91360 |
| Geologist | Barrett,, Mark A; Lic. No.: EG2088 | 14428 HAMLIN ST 200 VAN NUYS, CA 91401 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/24/2025 | Partial Approval | SEAN HAUPT |
| Pre-Inspection | 12/10/2025 | Partial Inspection | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 1/13/2026 | Conditional Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 1/13/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 1/13/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 1/16/2026 | Partial Approval | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 1/16/2026 | Partial Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 1/20/2026 | Partial Approval | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 1/20/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 1/21/2026 | Conditional Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 1/22/2026 | Partial Approval | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 1/22/2026 | Partial Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 2/12/2026 | Partial Approval | EVAN COOPER |
| Reinforced Concrete Frame | 2/12/2026 | Order to Comply Issued | EVAN COOPER |
| Deputy Reinf. Concrete | 2/13/2026 | Conditional Approval | DAVID FEILER |
| Piling/Pier/Caisson | 2/13/2026 | Partial Approval | RYAN SALAZAR |
| Piling/Pier/Caisson | 2/24/2026 | Partial Approval | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 3/20/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/2/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 4/3/2026 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 4/16/2026 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/16/2026 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 4/16/2026 | Partial Inspection | RYAN SALAZAR |
| Reinforced Concrete Frame | 5/18/2026 | Partial Approval | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 5/26/2026 | Conditional Approval | ANDREW NAVE |