12622 W SARAH ST 91604

Certificate Information: 12622 W SARAH ST 91604

Application / Permit
24014-10000-03685
Plan Check / Job No.
B24LA18848
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION/REMODEL TO (E) 1 STORY SFD AND PARTIALLY ENCLOSE (E) PATIO COVER AND EXPAND AREA .
Permit Issued
Issued on 9/11/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 NEHEMIAS RAMOS
Corrections Issued 8/24/2024 NEHEMIAS RAMOS
Building Plans Picked Up 8/28/2024 APPLICANT
Plan Check Approved 9/10/2024 CRISTINA SALAZAR
Issued 9/11/2024 APPLICANT
CofO in Progress 6/24/2025 CHRISTOPHE COCHRAN
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/26/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/26/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/26/2024 BIAINA HARITUNIAN
ZI Cleared 8/27/2024 ALEX VELA

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/4/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 11/7/2024 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/7/2024 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/15/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/13/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 1/13/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/15/2025 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 1/15/2025 Approved CHRISTOPHE COCHRAN
MERV13>=Rough 1/15/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 1/15/2025 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/28/2025 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/28/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 1/28/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 1/28/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 1/30/2025 Corrections Issued CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/30/2025 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 1/30/2025 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/3/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 2/3/2025 Approved CHRISTOPHE COCHRAN
Insulation 2/3/2025 Approved CHRISTOPHE COCHRAN
Shower Pan 2/3/2025 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 2/7/2025 Approved CHRISTOPHE COCHRAN
Shower Pan 2/7/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/20/2025 Approved CHRISTOPHE COCHRAN
Shower Pan 2/20/2025 Approved CHRISTOPHE COCHRAN
Final 6/20/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 6/20/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Final 6/20/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 6/20/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 6/24/2025 Approved CHRISTOPHE COCHRAN
Final 6/24/2025 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 6/24/2025 Approved CHRISTOPHE COCHRAN
HVAC-Final 6/24/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 6/24/2025 Approved CHRISTOPHE COCHRAN