611 N ALTA VISTA BLVD 90036
Certificate Information: 611 N ALTA VISTA BLVD 90036
- Application / Permit
- 24014-10000-03681
- Plan Check / Job No.
- B24LA18797
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED GARAGE CONVERSION INTO A.D.U. WITH PATIO COVER AND REAR ADDITIONS PER GC 66323
- Permit Issued
- Issued on 3/18/2025
- Issuing Office
- Current Status
- Issued on 3/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/24/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/30/2024 | APPLICANT |
| Applicant returned to address corrections | 2/7/2025 | NGHI SU |
| Applicant returned to address corrections | 3/4/2025 | CARLOS MONTES |
| Applicant returned to address corrections | 3/6/2025 | MINA HABILI |
| Applicant returned to address corrections | 3/13/2025 | CRISTINA SALAZAR |
| Plan Check Approved | 3/14/2025 | SHANGQIN XIE |
| Issued | 3/18/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 8/27/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2024 | CELINA MORENO |
| Sewer availability | Cleared | 8/30/2024 | CELINA MORENO |
| Construction near power lines | Cleared | 1/31/2025 | EDGAR PASCUA |
Contact Information
| Contractor | Ash Construction And Development Inc; Lic. No.: 1076076-B | 289 S ROBERTSON BLVD UNIT 215 BEVERLY HILLS, CA 90211 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/4/2025 | Conditional Approval | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 4/10/2025 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 4/14/2025 | Approved | JOSE MACIAS |
| Wood Frame | 5/6/2025 | Corrections Issued | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Partial Approval | JOSE MACIAS |
| Sewer | 5/20/2025 | Not Ready for Inspection | JOSE MACIAS |
| Sewer | 5/22/2025 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 5/23/2025 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 5/28/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 5/28/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 5/28/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/5/2025 | Approved | JOSE MACIAS |
| Shower Pan | 6/5/2025 | Approved | JOSE MACIAS |
| Insulation | 6/11/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/11/2025 | Not Ready for Inspection | JOSE MACIAS |
| Drywall Nailing | 6/12/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/12/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 9/18/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 9/18/2025 | Approved | JOSE MACIAS |
| Final | 9/18/2025 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 9/18/2025 | Approved | JOSE MACIAS |
| Green Building Final | 9/18/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 9/18/2025 | Approved | JOSE MACIAS |
| HVAC-Final | 9/18/2025 | Approved | JOSE MACIAS |
| METHANE-Barrier | 9/18/2025 | Approved | JOSE MACIAS |
| METHANE-Final | 9/18/2025 | Approved | JOSE MACIAS |
| METHANE-Rough | 9/18/2025 | Approved | JOSE MACIAS |
| METHANE-Subgrade | 9/18/2025 | Approved | JOSE MACIAS |
| PLUMBING-Final | 9/18/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 9/18/2025 | Approved | JOSE MACIAS |