2121 E 110TH ST 90059
Certificate Information: 2121 E 110TH ST 90059
- Application / Permit
- 24014-10000-03668
- Plan Check / Job No.
- B24LA18618
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. - New One Story Addition (enlarge kitchen, and new master bedroom, bathroom and closet) - Enlarge Kitchen and - New Covered Patio.
- Permit Issued
- Issued on 1/20/2025
- Issuing Office
- Current Status
- Issued on 1/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2024 | ZAW HAN |
| Corrections Issued | 9/3/2024 | ZAW HAN |
| Plan Check Approved | 1/17/2025 | ZAW HAN |
| Issued | 1/20/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/6/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 12/9/2024 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/2/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/17/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/22/2025 | No Access for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 5/23/2025 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2025 | Not Ready for Inspection | JOHN KLARIN |
| Insulation | 6/20/2025 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 6/20/2025 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Corrections Issued | ANTHONY EGSON |
| Insulation | 6/24/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Approved | JOHN KLARIN |
| Insulation | 7/1/2025 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 8/26/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Corrections Issued | ANTHONY EGSON |
| Insulation | 10/27/2025 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 10/27/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Wood Construction | 10/29/2025 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/26/2025 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 11/26/2025 | Conditional Approval | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 12/3/2025 | Approved | ARTHUR NEGRETE |
| Gas Test | 12/3/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 12/3/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 12/3/2025 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 12/3/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 12/16/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 12/16/2025 | Partial Inspection | ARTHUR NEGRETE |
| Shower Pan | 12/16/2025 | Partial Approval | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 12/24/2025 | Approved | ARTHUR NEGRETE |
| Shower Pan | 12/24/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 5/6/2026 | Corrections Issued | ARTHUR NEGRETE |
| Final | 5/6/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 5/6/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 5/6/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Final | 5/6/2026 | Corrections Issued | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Not Ready | ARTHUR NEGRETE |
| Smoke Detectors | 5/6/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 5/15/2026 | Approved | ARTHUR NEGRETE |
| Final | 5/15/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 5/15/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 5/15/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/15/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Final | 5/22/2026 | Not Ready for Inspection | ARTHUR NEGRETE |