589 N WILCOX AVE 90004
Certificate Information: 589 N WILCOX AVE 90004
- Application / Permit
- 24014-10000-03653
- Plan Check / Job No.
- B24LA18521
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] Convert portion of (E) Garage To ADU with a 1st and 2nd story addition per LAMC 12.22A.33 (c)-(d) -Bldg Sprinklered Thru-Out
- Permit Issued
- Issued on 2/17/2025
- Issuing Office
- Current Status
- Issued on 2/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 9/12/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/25/2024 | TU HUA |
| Applicant returned to address corrections | 12/26/2024 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 1/22/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 2/10/2025 | MAHNAZ NOURHASHEMI |
| Issued | 2/17/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/16/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 10/22/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 11/4/2024 | JESSICA OPINION |
| HPOZ | Cleared | 12/3/2024 | SUKI GERSHENHORN |
| Miscellaneous | Cleared | 12/3/2024 | SUKI GERSHENHORN |
Contact Information
| Contractor | F2c Builders Group Inc; Lic. No.: 1122970-B | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/26/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 6/23/2025 | Partial Inspection | JEFFREY MEAD |
| METHANE-Barrier | 6/23/2025 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 6/23/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 7/9/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 7/18/2025 | Not Ready for Inspection | BARRY HACHE |
| Footing/Foundation/Slab | 7/28/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 7/30/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Partial Approval | JEFFREY MEAD |
| Special/Order Compliance | 8/12/2025 | Approved | JEFFREY MEAD |
| Sewer | 9/8/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 9/8/2025 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 9/22/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2025 | Partial Approval | JOSH MEISTER |
| ELECTRICAL-Rough | 10/8/2025 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 10/8/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 10/8/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/14/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 10/14/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Shower Pan | 11/3/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/14/2025 | Conditional Approval | JEFFREY MEAD |
| Green Building Rough | 11/14/2025 | Approved | JEFFREY MEAD |
| METHANE-Rough | 11/14/2025 | Approved | JEFFREY MEAD |
| Insulation | 12/8/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 12/8/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 12/12/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 12/12/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/13/2026 | Partial Approval | JOSH MEISTER |
| PLUMBING-Rough | 4/13/2026 | Partial Approval | JOSH MEISTER |