2656 N SKYWIN WAY 90046
Certificate Information: 2656 N SKYWIN WAY 90046
- Application / Permit
- 24014-10000-03650
- Plan Check / Job No.
- B24LA18507
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2'-8"X14'-5 1/2" ADDITION TO AND REMODEL (E) SFD TO ENLARGE KITCHEN AND CONVERT PANTRY ROOM TO PART OF STUDY ROOM.
- Permit Issued
- Issued on 8/21/2025
- Issuing Office
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2024 | KAMYAR EMAMI |
| Corrections Issued | 8/26/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 7/26/2025 | KAMYAR EMAMI |
| Plan Check Approved | 8/19/2025 | KAMYAR EMAMI |
| Issued | 8/21/2025 | APPLICANT |
| CofO in Progress | 2/23/2026 | DAVID WILLIAMS |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/7/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2025 | LIAM ODONOVAN |
| ZA Case | Cleared | 6/6/2025 | DANIEL CORONADO |
| Specific Plan | Cleared | 6/18/2025 | JUDE HERNANDEZ |
| ZI | Cleared | 6/18/2025 | JUDE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 8/19/2025 | KAMYAR EMAMI |
Contact Information
| Contractor | Ene Builders; Lic. No.: 1113906-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/22/2025 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 9/29/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/12/2025 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 11/12/2025 | Approved | ROY SPAULDING |
| HVAC-Rough | 11/12/2025 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Rough | 11/12/2025 | Approved | ROY SPAULDING |
| Deputy Wood Construction | 11/13/2025 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 11/20/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 11/20/2025 | Approved | ROY SPAULDING |
| Underground Mechanical | 11/20/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/21/2025 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 11/24/2025 | Approved | ROY SPAULDING |
| Insulation | 11/24/2025 | Approved | ROY SPAULDING |
| Drywall Nailing | 11/26/2025 | Approved | CRAIG VAUGHAN |
| Final | 2/18/2026 | Corrections Issued | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 2/18/2026 | Approved | DAVID WILLIAMS |
| Final | 2/23/2026 | OK to Issue CofO | DAVID WILLIAMS |