526-526 1/2 W 49TH ST 90037
Certificate Information: 526-526 1/2 W 49TH ST 90037
- Application / Permit
- 24014-10000-03645
- Plan Check / Job No.
- B24LA18446
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ADDITION AT REAR OF EXISTING SFD FOR 2ND UNIT TO CONVERT SFD TO DUPLEX. WORK PER WFPP
- Permit Issued
- Issued on 9/5/2024
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 7/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/17/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/21/2024 | APPLICANT |
| Applicant returned to address corrections | 8/23/2024 | YAQUB MIRZA |
| Applicant returned to address corrections | 8/30/2024 | MINA HABILI |
| Plan Check Approved | 9/5/2024 | JOSEPH RAFOLS |
| Issued | 9/5/2024 | APPLICANT |
| CofO in Progress | 7/8/2025 | JOSE MACIAS |
| No Progress | 7/20/2025 | DEROLD HAUFF |
| CofO in Progress | 7/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/22/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2024 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 8/22/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 8/22/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/20/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/20/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 2/26/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 2/26/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 2/26/2025 | Partial Approval | LUIS CASTRO |
| Sewer | 2/26/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Approved | BARRY HACHE |
| Green Building Rough | 3/6/2025 | Not Ready for Inspection | BARRY HACHE |
| MERV13>=Rough | 3/6/2025 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 4/24/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/24/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/24/2025 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 4/28/2025 | Corrections Issued | BARRY HACHE |
| Wood Frame | 4/28/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 4/30/2025 | Approved | BARRY HACHE |
| Wood Frame | 4/30/2025 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 5/2/2025 | Approved | BARRY HACHE |
| Green Building Rough | 5/2/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 5/2/2025 | Partial Approval | BARRY HACHE |
| MERV13>=Rough | 5/2/2025 | Approved | BARRY HACHE |
| Insulation | 5/6/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 5/9/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 5/19/2025 | Approved | BARRY HACHE |
| Gas Test | 6/9/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 6/9/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 6/9/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 6/11/2025 | Corrections Issued | BARRY HACHE |
| Gas Test | 6/11/2025 | Approved | BARRY HACHE |
| HVAC-Final | 6/11/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 6/11/2025 | Approved | BARRY HACHE |
| Service/Power Release | 6/11/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 6/16/2025 | Corrections Issued | BARRY HACHE |
| Gas Test | 6/16/2025 | Approved | BARRY HACHE |
| HVAC-Final | 6/16/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 6/16/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 6/16/2025 | SGSOV Approved | BARRY HACHE |
| ELECTRICAL-Final | 6/18/2025 | Approved | BARRY HACHE |
| Final | 6/18/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 6/18/2025 | Approved | BARRY HACHE |
| HVAC-Final | 6/18/2025 | Approved | BARRY HACHE |
| MERV13>=Final | 6/18/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 6/18/2025 | Approved | BARRY HACHE |
| Service/Power Release | 6/18/2025 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 6/18/2025 | Approved | BARRY HACHE |
| Final | 6/24/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 6/25/2025 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 6/25/2025 | Approved | JOSE MACIAS |