16360 W SHADOW MOUNTAIN DR 90272
Certificate Information: 16360 W SHADOW MOUNTAIN DR 90272
- Application / Permit
- 24014-10000-03637
- Plan Check / Job No.
- B24LA18325
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Extension of a 10'x85' cantilevered deck to the existing deck.
- Permit Issued
- Issued on 1/13/2025
- Issuing Office
- Current Status
- Permit Finaled on 9/26/2025
Permit Application Status History
| Submitted | 8/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 8/17/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/22/2024 | YOUNG KIM |
| Plan Check Approved | 11/14/2024 | ARSALAN SHABESTARI |
| Issued | 1/13/2025 | APPLICANT |
| Permit Finaled | 9/25/2025 | TEMISTOCLES CAAL |
Permit Application Clearance Information
| ZA Case | Cleared | 9/4/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 9/4/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 9/4/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 9/4/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 9/4/2024 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 10/11/2024 | ANTHONY MAINEZ |
| Coastal Zone | Cleared | 10/30/2024 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2024 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 11/14/2024 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Handcrafted Construction Inc; Lic. No.: 841160-B | , |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/19/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 3/20/2025 | Conditional Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 3/24/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 3/25/2025 | Approved | BOBBY KEY |
| Structural Steel Frame | 3/25/2025 | Approved | BOBBY KEY |
| Final | 6/9/2025 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 6/9/2025 | Approved | TEMISTOCLES CAAL |
| Final | 9/25/2025 | Permit Finaled | TEMISTOCLES CAAL |