8023 N GARDEN GROVE AVE 91335
Certificate Information: 8023 N GARDEN GROVE AVE 91335
- Application / Permit
- 24014-10000-03635
- Plan Check / Job No.
- B24LA18316
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DET GARAGE AND (N) ADDITION TO ACCESSORY DWELLING UNIT WITH (N) PORCH PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 1/28/2025
- Issuing Office
- Current Status
- CofO Issued on 8/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/20/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 9/17/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 9/24/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 10/23/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 10/29/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 1/27/2025 | ISIS ARGUETA |
| Issued | 1/28/2025 | APPLICANT |
| CofO in Progress | 7/23/2025 | JUAN ALVARADO |
| Permit Finaled | 8/12/2025 | JOHN JANSON |
| CofO Issued | 8/12/2025 | JOHN JANSON |
| Permit Finaled | 8/12/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/11/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/11/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/11/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 12/31/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Morales,, Wilfrido; Lic. No.: C67533 | 6834 GEORGIA AVE BELL, CA 90201 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/24/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 2/26/2025 | Corrections Issued | JUAN ALVARADO |
| Sewer | 2/26/2025 | Approved | JUAN ALVARADO |
| Footing/Foundation/Slab | 3/3/2025 | Partial Approval | JUAN ALVARADO |
| Sewer | 3/3/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Footing/Foundation/Slab | 3/20/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 4/15/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Partial Approval | JUAN ALVARADO |
| HVAC-Rough | 4/15/2025 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Rough | 4/15/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Wood Frame | 4/15/2025 | Partial Approval | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2025 | Approved | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 4/25/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Underground Mechanical | 4/25/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 4/30/2025 | Approved | JUAN ALVARADO |
| Gas Test | 4/30/2025 | Not Ready for Inspection | JUAN ALVARADO |
| HVAC-Rough | 4/30/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Interior/Exterior Lathing | 4/30/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 4/30/2025 | Corrections Issued | JUAN ALVARADO |
| Gas Test | 5/5/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 5/5/2025 | Conditional Approval | JUAN ALVARADO |
| PLUMBING-Rough | 5/5/2025 | Approved | JUAN ALVARADO |
| Wood Frame | 5/5/2025 | Conditional Approval | JUAN ALVARADO |
| BUILDING-Rough-Frame | 5/9/2025 | Corrections Issued | HENRY KIM |
| Green Building Rough | 5/9/2025 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 5/9/2025 | Corrections Issued | HENRY KIM |
| Sewer | 5/9/2025 | Not Ready for Inspection | HENRY KIM |
| Smoke Detectors | 5/9/2025 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 5/9/2025 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 5/13/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 5/13/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 5/13/2025 | Approved | JUAN ALVARADO |
| Insulation | 5/13/2025 | Conditional Approval | JUAN ALVARADO |
| Underground Mechanical | 5/13/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Drywall Nailing | 5/28/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 5/28/2025 | Partial Approval | JUAN ALVARADO |
| Interior/Exterior Lathing | 6/11/2025 | Approved | JUAN ALVARADO |
| Pre-Inspection | 6/11/2025 | Approved | JUAN ALVARADO |
| Sewer | 6/25/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 6/25/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 7/14/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 7/14/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 7/14/2025 | Approved | JUAN ALVARADO |
| HVAC-Final | 7/14/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 7/14/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV Not Ready | JUAN ALVARADO |
| Smoke Detectors | 7/14/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 7/17/2025 | Approved | JUAN ALVARADO |
| Final | 7/17/2025 | Corrections Issued | JUAN ALVARADO |
| HVAC-Final | 7/17/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 7/17/2025 | Approved | JUAN ALVARADO |
| Final | 7/22/2025 | OK to Issue CofO | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Approved | JUAN ALVARADO |