425 E 91ST ST 90003

Certificate Information: 425 E 91ST ST 90003

Application / Permit
24014-10000-03623
Plan Check / Job No.
B24LA18178
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached Garage with Addition to detached Accessory Dwelling Unit per engineered design (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d)).
Permit Issued
Issued on 1/17/2025
Issuing Office
Metro
Current Status
CofO Issued on 8/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 GEORGE ALVAREZ
Corrections Issued 8/17/2024 GEORGE ALVAREZ
Building Plans Picked Up 8/20/2024 APPLICANT
Plan Check Approved 10/25/2024 AUNG SOE
Issued 1/17/2025 APPLICANT
No Progress 8/3/2025 DEROLD HAUFF
CofO in Progress 8/3/2025 DEROLD HAUFF
CofO in Progress 8/4/2025 MICHAEL LEWIS
Permit Finaled 8/5/2025 DEROLD HAUFF
CofO Issued 8/5/2025 DEROLD HAUFF
Permit Finaled 8/5/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/10/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 9/10/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 9/20/2024 CHRISTINA BRACO
Sewer availability Cleared 10/16/2024 CHRISTINA BRACO

Contact Information

Contractor Hernandez Christopher J Construction Services; Lic. No.: 800526-B PO BOX 11323      WHITTIER, CA 90603
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/23/2025 Partial Inspection JOHN QUINTANILLA
Footing/Foundation/Slab 1/30/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 2/20/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 2/26/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 2/26/2025 Approved JOHN QUINTANILLA
Underground Mechanical 2/26/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 3/5/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Approved JOHN QUINTANILLA
Green Building Rough 3/5/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 3/5/2025 Approved JOHN QUINTANILLA
Green Building Rough 3/7/2025 Approved JOHN QUINTANILLA
Insulation 3/7/2025 Approved JOHN QUINTANILLA
Drywall Nailing 3/13/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 3/13/2025 Approved ANTHONY RAMOS
Final 6/20/2025 Corrections Issued JOSE MACIAS
Green Building Final 6/20/2025 Not Ready for Inspection JOSE MACIAS
Smoke Detectors 6/20/2025 Approved JOSE MACIAS
Service/Power Release 6/23/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 7/18/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 7/18/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Approved JOHN QUINTANILLA
Final 7/23/2025 Conditional Approval JOHN QUINTANILLA
Final 7/30/2025 OK to Issue CofO BARRY HACHE
Service/Power Release 7/30/2025 Approved BARRY HACHE