8141 W CORNETT DR 90046
Certificate Information: 8141 W CORNETT DR 90046
- Application / Permit
- 24014-10000-03622
- Plan Check / Job No.
- B24LA18176
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to Single Family Residence: new primary suite; new bedroom & bath; new powder room & laundry; new kitchen. And Existing garage remodel.
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- Current Status
- Issued on 6/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2024 | JOE VO |
| Corrections Issued | 8/22/2024 | JOE VO |
| Quality Review Completed | 8/22/2024 | PRANITA SHAH |
| Plan Check Approved | 5/19/2025 | JOE VO |
| Issued | 6/23/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/19/2024 | JOE VO |
| BHO/Hillside ordinance | Cleared | 9/1/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 9/1/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 9/1/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 11/13/2024 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2024 | KIMBERLY HERNANDEZ |
| Specific Plan | Cleared | 1/23/2025 | JUDE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 1/25/2025 | LIAM ODONOVAN |
| Miscellaneous | Cleared | 2/18/2025 | JOE VO |
| BHO/Hillside ordinance | Cleared | 5/8/2025 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 5/8/2025 | KIMBERLY HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Song,, Zhenyu Michael; Lic. No.: NA5266 | , |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/26/2025 | Partial Inspection | RAUL BARAJAS |
| Pre-Inspection | 7/15/2025 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 8/8/2025 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/15/2025 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/15/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 8/19/2025 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/19/2025 | Approved | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 8/20/2025 | Conditional Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 12/9/2025 | Partial Inspection | ALEX COLIN |
| BUILDING-Rough-Frame | 12/12/2025 | Approved | DAVID WILLIAMS |
| Deck | 12/12/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 12/12/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 12/12/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 12/12/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 12/12/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 12/12/2025 | Approved | DAVID WILLIAMS |
| Shower Pan | 12/12/2025 | Approved | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 12/12/2025 | Approved | DAVID WILLIAMS |
| Insulation | 12/16/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 12/23/2025 | Approved | DAVID WILLIAMS |
| Special/Order Compliance | 5/19/2026 | Not Ready for Inspection | BRENDAN MORELLI |