2355 N GLOVER PL 90031
Certificate Information: 2355 N GLOVER PL 90031
- Application / Permit
- 24014-10000-03616
- Plan Check / Job No.
- B24LA18079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: REMOVE ATTACHED PATIO COVER, MAJOR ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING TO CREATE (N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. 13D FIRE SPRINKLER.
- Permit Issued
- Issued on 2/6/2025
- Issuing Office
- Current Status
- CofO Issued on 2/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2024 | DANIEL YIP |
| Corrections Issued | 8/17/2024 | DANIEL YIP |
| Quality Review Completed | 8/20/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 10/18/2024 | DANIEL YIP |
| Applicant returned to address corrections | 11/22/2024 | DANIEL YIP |
| Applicant returned to address corrections | 12/18/2024 | DANIEL YIP |
| Plan Check Approved | 2/5/2025 | DANIEL YIP |
| Issued | 2/6/2025 | APPLICANT |
| CofO in Progress | 2/5/2026 | HAMIK HARTOUNIAN |
| Permit Finaled | 2/6/2026 | DEROLD HAUFF |
| Permit Finaled | 2/6/2026 | DEROLD HAUFF |
| CofO Issued | 2/6/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 8/22/2024 | JILVER MAZARIEGOS |
| Roof/Waste drainage to street | Cleared | 8/30/2024 | KHAING AYE |
| ZI | Cleared | 8/30/2024 | JASON CHAN |
| Hydrant and Access approval | Cleared | 11/26/2024 | JOHN CONNEALLY |
| Trees in Parkway | Cleared | 2/4/2025 | RICHARD SANCHEZ |
Contact Information
| Architect | Abdelsayed,, Marc A; Lic. No.: C38176 | 280 VIA LINDA VISTA REDONDO BEACH, CA 90277 |
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/12/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/24/2025 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 3/24/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 4/1/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 4/2/2025 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/2/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 5/1/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Sewer | 5/2/2025 | Approved | ALEX COLIN |
| Underground Mechanical | 5/2/2025 | Partial Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 5/22/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/29/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/29/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/2/2025 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/10/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/20/2025 | Approved | REGINA MENDEZ |
| Insulation | 6/24/2025 | Not Ready for Inspection | ALEX COLIN |
| Shower Pan | 6/24/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 6/25/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Rough | 6/25/2025 | Approved | WILLIAM SIERRA |
| Insulation | 6/27/2025 | Conditional Approval | ALEX COLIN |
| Drywall Nailing | 7/8/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 7/15/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/16/2025 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 12/10/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 12/10/2025 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 12/10/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 12/10/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 1/21/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/21/2026 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/28/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 1/28/2026 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 1/28/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 2/5/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |