17344 W KINGSBURY ST 91344
Certificate Information: 17344 W KINGSBURY ST 91344
- Application / Permit
- 24014-10000-03602
- Plan Check / Job No.
- B24LA17909
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND ALTERATION TO THE EXISTING SFD. INCLUDING STRUCTURAL REMODEL AND REMOVE AND REFRAME PORTION OF ROOF AND NEW ROOF SHAPE.
- Permit Issued
- Issued on 9/30/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 8/17/2024 | NEHEMIAS RAMOS |
| Building Plans Picked Up | 8/21/2024 | APPLICANT |
| Plan Check Approved | 9/27/2024 | JOHN MESIAS |
| Issued | 9/30/2024 | APPLICANT |
| CofO in Progress | 7/8/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 7/22/2025 | RUBEN SALAS |
| CofO Issued | 7/22/2025 | RUBEN SALAS |
| Permit Finaled | 7/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/5/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/11/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/10/2024 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 10/22/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 10/22/2024 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 10/24/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/28/2024 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 10/28/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/28/2024 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Partial Inspection | JAVIER RAMOS JR |
| Wood Frame | 11/25/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/30/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/30/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 12/30/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/30/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/30/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 12/30/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 1/31/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/31/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 3/7/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 6/27/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 6/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Final | 6/27/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 6/27/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 7/7/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Green Building Final | 7/7/2025 | Approved | NICHOLAS TROWBRIDGE |