220 N SERRANO AVE 90004
Certificate Information: 220 N SERRANO AVE 90004
- Application / Permit
- 24014-10000-03601
- Plan Check / Job No.
- B24LA17900
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Addition and Convert existing detached garage to new detached Accessory dwelling unit per LAMC 12.22 A 33.(c) AND (d). All work per engineer. "COMPLY WITH DEPARTMENT ORDER effective date 07/09/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 1/3/2025
- Issuing Office
- Current Status
- CofO Issued on 11/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | PINANK PATEL |
| Corrections Issued | 8/19/2024 | PINANK PATEL |
| Applicant returned to address corrections | 12/11/2024 | PINANK PATEL |
| Plan Check Approved | 12/18/2024 | OMAR GARNICA |
| Issued | 1/3/2025 | APPLICANT |
| Permit Finaled | 11/26/2025 | CLAUDIO MORENO |
| CofO Issued | 11/26/2025 | CLAUDIO MORENO |
| Permit Finaled | 11/26/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 8/23/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 10/29/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 11/25/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Mirage Home Builders Inc; Lic. No.: 1100123-B | , |
| Engineer | Braun,, Jason; Lic. No.: C70948 | 14390 SHAWNEE ST MOORPARK, CA 93021 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/4/2025 | Corrections Issued | WILLIAM MICHALAK |
| PLUMBING-Rough | 2/4/2025 | Corrections Issued | WILLIAM MICHALAK |
| Deputy Drilled-In Anchors | 3/11/2025 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 5/20/2025 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Rough | 5/20/2025 | Approved | WILLIAM MICHALAK |
| Rough-Elec/Plmb/HVAC | 5/20/2025 | Approved | WILLIAM MICHALAK |
| Underground Mechanical | 5/20/2025 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 5/28/2025 | Corrections Issued | WILLIAM MICHALAK |
| Rough-Elec/Plmb/HVAC | 5/28/2025 | Partial Approval | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 6/4/2025 | Corrections Issued | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 7/3/2025 | Corrections Issued | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 7/8/2025 | Approved | WILLIAM MICHALAK |
| Final | 7/8/2025 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 7/8/2025 | Approved | WILLIAM MICHALAK |
| Green Building Final | 7/8/2025 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 7/8/2025 | SGSOV Approved | WILLIAM MICHALAK |
| Smoke Detectors | 7/8/2025 | Approved | WILLIAM MICHALAK |
| Final | 11/18/2025 | OK to Issue CofO | WILLIAM MICHALAK |