8621 S LILIENTHAL AVE 90045

Certificate Information: 8621 S LILIENTHAL AVE 90045

Application / Permit
24014-10000-03595
Plan Check / Job No.
B24LA17829
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SINGLE FAMILY DWELLING TO ATTACH TO EXISTING DETACHED GARAGE. FIRE SPRINKLERS THROUGH OUT (NFPA 13D) "COMPLY WITH DEPARTMENT ORDER effective date 11/10/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 1/3/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 SUNMIN LEE
Corrections Issued 8/17/2024 SUNMIN LEE
Building Plans Picked Up 8/24/2024 APPLICANT
Applicant returned to address corrections 9/13/2024 DANIEL SANJUAN
Plan Check Approved 11/14/2024 ALEXANDER JOO
Issued 1/3/2025 APPLICANT
CofO in Progress 3/16/2026 ANDREW BEELI
Permit Finaled 3/24/2026 CLAUDIO MORENO
CofO Issued 3/24/2026 CLAUDIO MORENO
Permit Finaled 3/24/2026 CLAUDIO MORENO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/28/2024 ANTHONY MAINEZ
Sewer availability Cleared 10/28/2024 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 10/29/2024 DIANA RENTERIA
Specific Plan Cleared 11/12/2024 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/17/2025 Partial Approval ANDREW BEELI
Footing/Foundation/Slab 1/23/2025 Approved ANDREW BEELI
BUILDING-Rough-Frame 2/5/2025 Partial Approval ANDREW BEELI
Green Building Rough 2/5/2025 Not Ready for Inspection ANDREW BEELI
PLUMBING-Rough 2/5/2025 Partial Approval ANDREW BEELI
BUILDING-Rough-Frame 2/11/2025 Not Ready for Inspection ANDREW BEELI
Green Building Rough 2/11/2025 Not Ready for Inspection ANDREW BEELI
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Approved ANDREW BEELI
Wood Frame 3/11/2025 Partial Inspection ANDREW BEELI
ELECTRICAL-Rough 3/21/2025 Corrections Issued ANDREW BEELI
Gas Test 3/21/2025 Corrections Issued ANDREW BEELI
HVAC-Rough 3/21/2025 Corrections Issued ANDREW BEELI
PLUMBING-Rough 3/21/2025 Approved ANDREW BEELI
BUILDING-Rough-Frame 3/26/2025 Approved ANDREW BEELI
Green Building Rough 3/26/2025 Approved ANDREW BEELI
Shower Pan 3/26/2025 Approved ANDREW BEELI
BUILDING-Rough-Frame 4/3/2025 Approved ANDREW BEELI
Green Building Rough 4/3/2025 Approved ANDREW BEELI
Insulation 4/3/2025 Approved ANDREW BEELI
Interior/Exterior Lathing 4/3/2025 Approved ANDREW BEELI
Drywall Nailing 4/8/2025 Approved RYAN BARNES
ELECTRICAL-Final 7/18/2025 Approved ANDREW BEELI
Final 7/18/2025 Partial Approval ANDREW BEELI
Green Building Final 7/18/2025 Approved ANDREW BEELI
PLUMBING-Final 7/18/2025 Approved ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Approved ANDREW BEELI
Smoke Detectors 7/18/2025 Approved ANDREW BEELI
ELECTRICAL-Rough 3/5/2026 Approved ANDREW BEELI
HVAC-Final 3/5/2026 Approved ANDREW BEELI
HVAC-Rough 3/5/2026 Approved ANDREW BEELI
Final 3/16/2026 OK to Issue CofO ANDREW BEELI