1024 S HAYWORTH AVE 90035

Certificate Information: 1024 S HAYWORTH AVE 90035

Application / Permit
24014-10000-03588
Plan Check / Job No.
B24LA17785
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
Eplan. Irregular shaped addition to detached garage to convert to 26' x 26' 6" garage/storage
Permit Issued
Issued on 4/30/2025
Issuing Office
Current Status
Issued on 4/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/28/2024 APPLICANT
Assigned to Plan Check Engineer 9/3/2024 KAMYAR EMAMI
Corrections Issued 9/4/2024 KAMYAR EMAMI
Applicant returned to address corrections 3/6/2025 NAREG ATARIAN
Applicant returned to address corrections 3/19/2025 KAMYAR EMAMI
Applicant returned to address corrections 3/26/2025 KAMYAR EMAMI
Plan Check Approved 4/12/2025 NAREG ATARIAN
Issued 4/30/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/30/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 1/30/2025 ADRIAN SANCHEZ
CPC Cleared 2/3/2025 DEBORAH MCGILL
HPOZ Cleared 2/3/2025 DEBORAH MCGILL
Historic monument Cleared 2/3/2025 DEBORAH MCGILL
ZI Cleared 2/3/2025 DEBORAH MCGILL

Contact Information

Contractor Deep Canyon Design + Build Corporation; Lic. No.: 1135670-B       ,
Engineer Standley,, Craig Erick; Lic. No.: NA87675       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2025 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 6/12/2025 Approved ARTHUR NEGRETE
METHANE-Barrier 6/12/2025 Approved ARTHUR NEGRETE
METHANE-Subgrade 6/12/2025 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 6/23/2025 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 6/26/2025 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 7/10/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Approved ARTHUR NEGRETE
Green Building Rough 8/26/2025 Approved ARTHUR NEGRETE
METHANE-Rough 8/26/2025 Approved ARTHUR NEGRETE
Wood Frame 8/26/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 12/8/2025 Approved BRENDAN MORELLI