4956 N HIGHLAND VIEW AVE 90041

Certificate Information: 4956 N HIGHLAND VIEW AVE 90041

Application / Permit
24014-10000-03576
Plan Check / Job No.
B24LA17702
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO EXISTING SINGLE CAR GARAGE AND CONVERT TO ADU PER ORDINANCE
Permit Issued
Issued on 9/5/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 MINA HABILI
Corrections Issued 8/17/2024 MINA HABILI
Building Plans Picked Up 8/21/2024 APPLICANT
Applicant returned to address corrections 9/4/2024 SUNMIN LEE
Plan Check Approved 9/5/2024 JOSEPH RAFOLS
Issued 9/5/2024 APPLICANT
CofO in Progress 5/13/2025 DAVID WILLIAMS
Permit Finaled 5/15/2025 DEROLD HAUFF
Permit Finaled 5/15/2025 DEROLD HAUFF
CofO Issued 5/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/22/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 8/22/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 8/22/2024 JUSTIN BICOL
Sewer availability Cleared 8/22/2024 JUSTIN BICOL
Grading Pre-Inspection Cleared 8/26/2024 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/27/2024 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 10/25/2024 Partial Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 11/7/2024 Approved ROY SPAULDING
Footing/Foundation/Slab 11/7/2024 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Approved BRENDAN MORELLI
ELECTRICAL-Rough 1/13/2025 Approved BRENDAN MORELLI
HVAC-Rough 1/13/2025 Approved BRENDAN MORELLI
PLUMBING-Rough 1/13/2025 Approved BRENDAN MORELLI
Drywall Nailing 1/23/2025 Partial Approval BRENDAN MORELLI
Shower Pan 1/23/2025 Approved BRENDAN MORELLI
Interior/Exterior Lathing 1/27/2025 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/29/2025 Approved BRENDAN MORELLI
Green Building Rough 1/29/2025 Approved BRENDAN MORELLI
Interior/Exterior Lathing 2/4/2025 Approved JOSH MEISTER
Insulation 2/6/2025 Approved BRENDAN MORELLI
Drywall Nailing 2/11/2025 Approved JOSH MEISTER
ELECTRICAL-Final 5/9/2025 Approved DAVID WILLIAMS
Final 5/9/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 5/9/2025 Approved DAVID WILLIAMS
HVAC-Final 5/9/2025 Approved DAVID WILLIAMS
PLUMBING-Final 5/9/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Approved DAVID WILLIAMS
Service/Power Release 5/9/2025 Approved DAVID WILLIAMS
Smoke Detectors 5/9/2025 Approved DAVID WILLIAMS
Final 5/13/2025 OK to Issue CofO DAVID WILLIAMS