6563 S HAAS AVE 90047

Certificate Information: 6563 S HAAS AVE 90047

Application / Permit
24014-10000-03566
Plan Check / Job No.
B24LA17590
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-Story ADU ground floor addition, per LAMC 12.22.A.33 (c) and (d), to an existing 1-story one-car garage (1930LA19889)
Permit Issued
Issued on 2/28/2025
Issuing Office
Metro
Current Status
Issued on 2/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/12/2024 APPLICANT
Assigned to Plan Check Engineer 8/20/2024 EDWIN MARTINEZ
Corrections Issued 8/26/2024 EDWIN MARTINEZ
Quality Review Completed 8/27/2024 KESETE HAREGOT
Quality Review Completed 8/28/2024 KESETE HAREGOT
Building Plans Picked Up 9/20/2024 APPLICANT
Plan Check Approved 2/18/2025 EDWIN MARTINEZ
Issued 2/28/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 11/20/2024 RIDWAN HARDY
Construction within easement Cleared 11/20/2024 RIDWAN HARDY
Address approval Cleared 12/9/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 1/24/2025 AMBER CAMPBELL
Sewer availability Cleared 1/24/2025 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 2/13/2025 AMBER CAMPBELL
Green Code Cleared 2/18/2025 EDWIN MARTINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/1/2025 Partial Approval BARRY HACHE
Footing/Foundation/Slab 7/8/2025 No Access for Inspection BARRY HACHE
Footing/Foundation/Slab 7/10/2025 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 7/24/2025 Partial Approval BARRY HACHE
Footing/Foundation/Slab 7/31/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 8/11/2025 Partial Approval WAYNE REGESTER
Green Building Rough 8/11/2025 Not Ready for Inspection WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 12/30/2025 Corrections Issued BARRY HACHE
Green Building Rough 12/30/2025 Not Ready for Inspection BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 1/12/2026 Corrections Issued BARRY HACHE
Green Building Rough 1/12/2026 Not Ready for Inspection BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 1/23/2026 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 1/26/2026 Corrections Issued BARRY HACHE
Interior/Exterior Lathing 1/26/2026 Partial Approval BARRY HACHE
PLUMBING-Rough 1/26/2026 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 2/27/2026 Partial Approval RAUL BARAJAS
PLUMBING-Rough 2/27/2026 Approved RAUL BARAJAS
Insulation 3/10/2026 Corrections Issued ALEX COLIN
BUILDING-Rough-Frame 3/13/2026 Corrections Issued RAUL BARAJAS
Green Building Rough 3/13/2026 Approved RAUL BARAJAS
ELECTRICAL-Rough 5/11/2026 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/11/2026 Approved LUIS CASTRO
Insulation 5/11/2026 Approved LUIS CASTRO
Insulation 5/12/2026 No Access for Inspection JOHN QUINTANILLA