17458 W DORIC ST 91344

Certificate Information: 17458 W DORIC ST 91344

Application / Permit
24014-10000-03552
Plan Check / Job No.
B24LA17384
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION & REMODEL TO (E) 2-STORY SFD.
Permit Issued
Issued on 2/21/2025
Issuing Office
Metro
Current Status
Issued on 2/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/9/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 ARSALAN SHABESTARI
Corrections Issued 8/18/2024 ARSALAN SHABESTARI
Quality Review Completed 8/23/2024 KEN GILL
Building Plans Picked Up 9/4/2024 APPLICANT
Plan Check Approved 2/5/2025 ARSALAN SHABESTARI
Issued 2/21/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/13/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/13/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/13/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/13/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/13/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/13/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/16/2024 CARLOS AGUILERA
Sewer availability Cleared 9/16/2024 CARLOS AGUILERA
Construction near power lines Cleared 10/18/2024 ENRIQUE ACOSTA
Construction within easement Cleared 10/18/2024 ENRIQUE ACOSTA
Miscellaneous Cleared 10/19/2024 CARLOS AGUILERA
ZA Case Cleared 12/27/2024 STEVEN WECHSLER
Grading Pre-Inspection Cleared 2/5/2025 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/7/2025 Partial Inspection STEVEN BACK
Underground Mechanical 5/1/2025 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 5/6/2025 Approved DAVID SCANTLIN
Deputy Drilled-In Anchors 5/13/2025 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 5/23/2025 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 5/28/2025 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 5/29/2025 Approved DAVID SCANTLIN
Deputy Steel/Welding 6/5/2025 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/10/2025 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 9/16/2025 Not Ready for Inspection STEVEN BACK
HVAC-Rough 10/1/2025 Approved STEVEN BACK
PLUMBING-Rough 10/1/2025 Approved STEVEN BACK
ELECTRICAL-Rough 11/6/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Approved STEVEN BACK
Interior/Exterior Lathing 12/12/2025 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 12/24/2025 Approved STEVEN BACK
Green Building Rough 12/24/2025 Approved STEVEN BACK
Insulation 12/24/2025 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 12/24/2025 Partial Approval STEVEN BACK
Insulation 1/6/2026 Approved GEVORK IPCHYAN
Drywall Nailing 1/26/2026 Approved STEVEN BACK
Interior/Exterior Lathing 1/26/2026 Approved STEVEN BACK
Underground Mechanical 5/19/2026 Approved STEVEN BACK