6080 W 82ND ST 90045

Certificate Information: 6080 W 82ND ST 90045

Application / Permit
24014-10000-03522
Plan Check / Job No.
B24LA17178
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and major remodel to existing 2-story single family dwelling per enigneer details.
Permit Issued
Issued on 12/13/2024
Issuing Office
West Los Angeles
Current Status
Issued on 12/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/8/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 VICTOR CHEN
Corrections Issued 8/21/2024 VICTOR CHEN
Quality Review Completed 8/23/2024 KEN GILL
Building Plans Picked Up 8/27/2024 APPLICANT
Applicant returned to address corrections 10/11/2024 VICTOR CHEN
Applicant returned to address corrections 10/24/2024 VICTOR CHEN
Plan Check Approved 11/8/2024 VICTOR CHEN
Issued 12/13/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/11/2024 BRENDEN HAWK
Eng Process Fee Ord 176,300 Cleared 9/14/2024 LIAM ODONOVAN
Sewer availability Cleared 9/14/2024 LIAM ODONOVAN
Specific Plan Cleared 9/23/2024 HAMID GHAEMMAGHAMI
Disturb/Remove Protected Trees Cleared 9/30/2024 MIGUEL ORNELAS

Contact Information

Architect Oreck,, Kevin Robert; Lic. No.: C23895 1008 LARKER AVE      LOS ANGELES, CA 90042
Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813
Engineer Yamashita,, Mark Alan; Lic. No.: L7155 6718 BIANCA AVE      LAKE BALBOA, CA 91406

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 3/3/2025 Not Ready for Inspection HERBERT GIRON
Special/Order Compliance 3/3/2025 Partial Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 6/2/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 6/4/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Conditional Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 10/22/2025 Conditional Approval DAVID FEILER
Deputy Wood Construction 10/22/2025 Conditional Approval DAVID FEILER
Pre-Inspection 10/23/2025 Partial Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/11/2026 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 5/11/2026 Not Ready for Inspection MICHAEL LEWIS
Green Building Rough 5/11/2026 Approved MICHAEL LEWIS
HVAC-Rough 5/11/2026 Approved MICHAEL LEWIS
Interior/Exterior Lathing 5/11/2026 Approved MICHAEL LEWIS
PLUMBING-Rough 5/11/2026 Approved MICHAEL LEWIS
ELECTRICAL-Rough 5/14/2026 Conditional Approval MICHAEL LEWIS
BUILDING-Rough-Frame 5/15/2026 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 5/15/2026 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/20/2026 Conditional Approval MICHAEL LEWIS
Verify Sprinkler Sign Off 5/20/2026 Approved MICHAEL LEWIS
Insulation 5/27/2026 Approved MORRIS JACKSON