8206 N WYNNE AVE 91335
Certificate Information: 8206 N WYNNE AVE 91335
- Application / Permit
- 24014-10000-03513
- Plan Check / Job No.
- B24LA17132
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: ADDITION TO (E) GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(C) AND (D)
- Permit Issued
- Issued on 12/24/2024
- Issuing Office
- Current Status
- CofO Issued on 9/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2024 | GURUNATH NESARAJAH |
| Corrections Issued | 8/14/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 11/21/2024 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/23/2024 | GURUNATH NESARAJAH |
| Issued | 12/24/2024 | APPLICANT |
| CofO in Progress | 8/21/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
| CofO Issued | 9/6/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 9/2/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 11/13/2024 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 11/18/2024 | ERIK BEASLEY |
| Construction near power lines | Cleared | 12/19/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 28025 DOROTHY DR STE 202 AGOURA HILLS, CA 91301 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/3/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Deputy Reinf. Concrete | 1/3/2025 | Conditional Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 1/7/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/7/2025 | Corrections Issued | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 1/7/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 1/14/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/14/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 2/19/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Rough | 2/19/2025 | Not Ready for Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 3/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 3/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 3/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/18/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2025 | Partial Approval | ARUTYUN MADATYAN |
| HVAC-Rough | 3/18/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/18/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/18/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 3/26/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/26/2025 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 4/1/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/1/2025 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 4/15/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 6/6/2025 | Approved | ARUTYUN MADATYAN |
| Final | 6/6/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 6/6/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 6/6/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 6/6/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 6/30/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 6/30/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Final | 6/30/2025 | Approved | JUAN ALVARADO |
| HVAC-Final | 6/30/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 6/30/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV Approved | JUAN ALVARADO |
| Service/Power Release | 6/30/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 6/30/2025 | Approved | JUAN ALVARADO |
| Final | 8/1/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 8/20/2025 | Approved | ARUTYUN MADATYAN |
| Final | 8/20/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Service/Power Release | 8/20/2025 | Approved | ARUTYUN MADATYAN |