9908 W ANTHONY PL 90210
Certificate Information: 9908 W ANTHONY PL 90210
- Application / Permit
- 24014-10000-03506
- Plan Check / Job No.
- B24LA17081
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Second story addition over garage in existing two story single family per engineer design FOOTING ENFORCEMENT ON FIRST FLOOR ***13D sprinkler***
- Permit Issued
- Issued on 11/1/2024
- Issuing Office
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2024 | KHUONG TRUONG |
| Corrections Issued | 8/17/2024 | KHUONG TRUONG |
| Quality Review Completed | 8/20/2024 | GARO TELMI |
| Applicant returned to address corrections | 9/5/2024 | KHUONG TRUONG |
| Plan Check Approved | 10/31/2024 | KHUONG TRUONG |
| Issued | 11/1/2024 | APPLICANT |
| CofO in Progress | 9/20/2025 | SEAN HAUPT |
| Permit Finaled | 9/25/2025 | RICHARD STEINBACH |
| CofO Issued | 9/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 8/19/2024 | VLADIMIR ARUTYUNYAN |
| ZA Case | Cleared | 8/26/2024 | MATHEW QUAN |
| BHO/Hillside ordinance | Cleared | 8/27/2024 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 8/27/2024 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 8/27/2024 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 8/27/2024 | KIMBERLY HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 9/4/2024 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 9/5/2024 | KHUONG TRUONG |
| Hydrant and Access approval | Cleared | 10/29/2024 | KURT CORRAL |
Contact Information
| Architect | Shahverdi,, Mehran; Lic. No.: C39691 | 23815 NORTHWOODS VIEW RD WEST HILLS, CA 91307 |
| Contractor | Owner-Builder | , |
| Engineer | Vahdat,, Siamak; Lic. No.: NA65255 | , |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/30/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 2/11/2025 | Corrections Issued | SEAN HAUPT |
| Deputy Drilled-In Anchors | 2/12/2025 | Partial Approval | SEAN HAUPT |
| Deputy Drilled-In Anchors | 2/14/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 2/18/2025 | Approved | SEAN HAUPT |
| Deputy Drilled-In Anchors | 2/28/2025 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/4/2025 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 4/11/2025 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 4/16/2025 | Partial Approval | SEAN HAUPT |
| Interior/Exterior Lathing | 4/16/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/21/2025 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 4/21/2025 | Approved | SEAN HAUPT |
| Green Building Rough | 4/21/2025 | Approved | SEAN HAUPT |
| HVAC-Rough | 4/21/2025 | Approved | SEAN HAUPT |
| Shower Pan | 4/21/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 5/15/2025 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 5/15/2025 | Approved | SEAN HAUPT |
| Insulation | 5/16/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/19/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 5/20/2025 | Approved | SEAN HAUPT |
| Sewer | 5/22/2025 | Approved | SEAN HAUPT |
| Final | 8/19/2025 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 8/19/2025 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 8/19/2025 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 8/19/2025 | Approved | SEAN HAUPT |
| Final | 9/19/2025 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 9/19/2025 | Approved | SEAN HAUPT |