9908 W ANTHONY PL 90210

Certificate Information: 9908 W ANTHONY PL 90210

Application / Permit
24014-10000-03506
Plan Check / Job No.
B24LA17081
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Second story addition over garage in existing two story single family per engineer design FOOTING ENFORCEMENT ON FIRST FLOOR ***13D sprinkler***
Permit Issued
Issued on 11/1/2024
Issuing Office
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 KHUONG TRUONG
Corrections Issued 8/17/2024 KHUONG TRUONG
Quality Review Completed 8/20/2024 GARO TELMI
Applicant returned to address corrections 9/5/2024 KHUONG TRUONG
Plan Check Approved 10/31/2024 KHUONG TRUONG
Issued 11/1/2024 APPLICANT
CofO in Progress 9/20/2025 SEAN HAUPT
Permit Finaled 9/25/2025 RICHARD STEINBACH
CofO Issued 9/25/2025 RICHARD STEINBACH
Permit Finaled 9/25/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/19/2024 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 8/19/2024 VLADIMIR ARUTYUNYAN
ZA Case Cleared 8/26/2024 MATHEW QUAN
BHO/Hillside ordinance Cleared 8/27/2024 KIMBERLY HERNANDEZ
BHO/Hillside ordinance Cleared 8/27/2024 KIMBERLY HERNANDEZ
BHO/Hillside ordinance Cleared 8/27/2024 KIMBERLY HERNANDEZ
BHO/Hillside ordinance Cleared 8/27/2024 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 9/4/2024 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 9/5/2024 KHUONG TRUONG
Hydrant and Access approval Cleared 10/29/2024 KURT CORRAL

Contact Information

Architect Shahverdi,, Mehran; Lic. No.: C39691 23815 NORTHWOODS VIEW RD      WEST HILLS, CA 91307
Contractor Owner-Builder       ,
Engineer Vahdat,, Siamak; Lic. No.: NA65255       ,

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/30/2025 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 2/11/2025 Corrections Issued SEAN HAUPT
Deputy Drilled-In Anchors 2/12/2025 Partial Approval SEAN HAUPT
Deputy Drilled-In Anchors 2/14/2025 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 2/18/2025 Approved SEAN HAUPT
Deputy Drilled-In Anchors 2/28/2025 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 4/4/2025 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 4/11/2025 Approved SEAN HAUPT
ELECTRICAL-Rough 4/16/2025 Partial Approval SEAN HAUPT
Interior/Exterior Lathing 4/16/2025 Approved SEAN HAUPT
BUILDING-Rough-Frame 4/21/2025 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 4/21/2025 Approved SEAN HAUPT
Green Building Rough 4/21/2025 Approved SEAN HAUPT
HVAC-Rough 4/21/2025 Approved SEAN HAUPT
Shower Pan 4/21/2025 Approved SEAN HAUPT
BUILDING-Rough-Frame 5/15/2025 Approved SEAN HAUPT
Verify Sprinkler Sign Off 5/15/2025 Approved SEAN HAUPT
Insulation 5/16/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 5/19/2025 Approved DANIEL VERA
Drywall Nailing 5/20/2025 Approved SEAN HAUPT
Sewer 5/22/2025 Approved SEAN HAUPT
Final 8/19/2025 Corrections Issued SEAN HAUPT
Green Building Final 8/19/2025 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Approved SEAN HAUPT
Smoke Detectors 8/19/2025 Approved SEAN HAUPT
Final 9/19/2025 OK to Issue CofO SEAN HAUPT
Green Building Final 9/19/2025 Approved SEAN HAUPT