3909 S ORANGE DR 90008
Certificate Information: 3909 S ORANGE DR 90008
- Application / Permit
- 24014-10000-03504
- Plan Check / Job No.
- B24LA17045
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: 3'-1" X 15'-3" 1ST STORY ADDITION, 4'-0" X 20'-8" 1STORY ADDITION, AND 6'-0" X 20'-8" FRONT PORCH ADDITION, AND REFRAME PORTION OF EXISITNG ROOF, EXTEND 11'-10" X 5'-8" PORTION AT SECOND STORY ROOF FOR STAIR CASE. ALL WORK PER ENG.
- Permit Issued
- Issued on 6/4/2025
- Issuing Office
- Current Status
- Issued on 6/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/20/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 9/24/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 10/19/2024 | LUISANGEL VALENZUELA |
| Issued | 6/4/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/21/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 8/21/2024 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 9/9/2024 | MICHAEL TEMPLE |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2024 | TREVOR QUAN |
Contact Information
| Contractor | U S Home Developers Inc; Lic. No.: 947505-B | , |
| Contractor | Us Home Developers Inc; Lic. No.: 947505-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/16/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 9/10/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 9/10/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 9/10/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 9/16/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Rough | 9/16/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 9/16/2025 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 9/18/2025 | Approved | LUIS CASTRO |
| Insulation | 9/18/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 9/25/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 9/25/2025 | Approved | RONNIE MEDINA |
| Shower Pan | 9/25/2025 | Approved | RONNIE MEDINA |
| ELECTRICAL-Final | 12/23/2025 | Approved | LUIS CASTRO |
| Final | 12/23/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 12/23/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 12/23/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 12/23/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 12/23/2025 | Approved | LUIS CASTRO |