2148 3/4 W 30TH ST 90018
Certificate Information: 2148 3/4 W 30TH ST 90018
- Application / Permit
- 24014-10000-03489
- Plan Check / Job No.
- B24LA16932
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Addition and conversion of existing detached garage to A.D.U. per LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 8/14/2025
- Issuing Office
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2024 | CAROLEAN BASMA |
| Corrections Issued | 8/22/2024 | CAROLEAN BASMA |
| Plan Check Approved | 8/13/2025 | REZA HAGHIGHAT |
| Issued | 8/14/2025 | APPLICANT |
| CofO in Progress | 1/20/2026 | SABAS ALONSO |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
| CofO Issued | 1/21/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/5/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 9/5/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 9/18/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 12/4/2024 | TINA MIRANDA |
| HPOZ | Cleared | 2/11/2025 | DANIEL MATA |
Contact Information
| Contractor | Next Level Home Improvements; Lic. No.: 1120800-B | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/18/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 8/21/2025 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 8/21/2025 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 9/19/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 9/23/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 9/23/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 9/23/2025 | Corrections Issued | SABAS ALONSO |
| Sewer | 9/23/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 9/23/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 9/26/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/26/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 9/26/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/1/2025 | Approved | SABAS ALONSO |
| Shower Pan | 10/1/2025 | Corrections Issued | SABAS ALONSO |
| Insulation | 10/10/2025 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 10/10/2025 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 10/15/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 10/15/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 10/15/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 10/21/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 11/26/2025 | Approved | SABAS ALONSO |
| Final | 12/11/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/11/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/11/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 12/11/2025 | Approved | SABAS ALONSO |
| Final | 1/13/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 1/13/2026 | Approved | SABAS ALONSO |
| Final | 1/16/2026 | OK to Issue CofO | SABAS ALONSO |