5700 S 9TH AVE 90043

Certificate Information: 5700 S 9TH AVE 90043

Application / Permit
24014-10000-03477
Plan Check / Job No.
B24LA16818
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
423 SQFT HOUSE ADDITION TO EXISTING SFD (ADD 2 BEDROOM), CHANGE SIDING TO STUCCO THROUGHOUT THE HOME.
Permit Issued
Issued on 9/13/2024
Issuing Office
Metro
Current Status
CofO Issued on 6/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2024 APPLICANT
Assigned to Plan Check Engineer 8/12/2024 LUKE GONZALES
Corrections Issued 8/13/2024 LUKE GONZALES
Building Plans Picked Up 8/16/2024 APPLICANT
Plan Check Approved 9/10/2024 JOSEPH RAFOLS
Issued 9/13/2024 APPLICANT
CofO in Progress 5/30/2025 LUIS CASTRO
Permit Finaled 6/1/2025 DEROLD HAUFF
CofO Issued 6/1/2025 DEROLD HAUFF
Permit Finaled 6/1/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/15/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/16/2024 DAVID VO
Sewer availability Cleared 8/16/2024 DAVID VO

Contact Information

Contractor Goliath Construction Corp; Lic. No.: 1072310-B 15758 PLUMMER ST      NORTH HILLS, CA 91343
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2024 Conditional Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 9/17/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 9/17/2024 Corrections Issued ANTHONY EGSON
Deputy Drilled-In Anchors 9/20/2024 Approved ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 9/20/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 9/20/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Partial Approval ANTHONY EGSON
Deputy Drilled-In Anchors 11/19/2024 Conditional Approval ANTHONY RAMOS
Deputy Wood Construction 11/19/2024 Conditional Approval ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Approved BARRY HACHE
ELECTRICAL-Rough 12/5/2024 Approved BARRY HACHE
HVAC-Rough 12/5/2024 Approved BARRY HACHE
Special/Order Compliance 12/5/2024 Approved BARRY HACHE
BUILDING-Rough-Frame 12/11/2024 Corrections Issued BRENDAN MORELLI
Green Building Rough 12/11/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 12/11/2024 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 12/11/2024 Approved BRENDAN MORELLI
Insulation 12/17/2024 Not Ready for Inspection ANTHONY RAMOS
Interior/Exterior Lathing 12/17/2024 Not Ready for Inspection ANTHONY RAMOS
Shower Pan 12/17/2024 Not Ready for Inspection ANTHONY RAMOS
Insulation 12/20/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 12/20/2024 Approved LUIS CASTRO
Shower Pan 12/20/2024 Corrections Issued LUIS CASTRO
BUILDING-Rough-Frame 12/24/2024 Approved LUIS CASTRO
Drywall Nailing 12/24/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 1/13/2025 Approved ARTHUR NEGRETE
Shower Pan 1/13/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 5/29/2025 Approved LUIS CASTRO
Final 5/29/2025 OK to Issue CofO LUIS CASTRO
Green Building Final 5/29/2025 Approved LUIS CASTRO
HVAC-Final 5/29/2025 Approved LUIS CASTRO
PLUMBING-Final 5/29/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 5/29/2025 Approved LUIS CASTRO