9110 W DAVID AVE 90034
Certificate Information: 9110 W DAVID AVE 90034
- Application / Permit
- 24014-10000-03473
- Plan Check / Job No.
- B24LA16802
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: (N) DECK, STAIR AND 1ST STORY ADDITOIN AND REMODEL TO (E) SINGLE FAMILY DWELLING WITH BASEMENT
- Permit Issued
- Issued on 11/6/2024
- Issuing Office
- Current Status
- CofO Issued on 2/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | DANIEL YIP |
| Corrections Issued | 8/10/2024 | DANIEL YIP |
| Quality Review Completed | 8/16/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 10/16/2024 | DANIEL YIP |
| Plan Check Approved | 11/1/2024 | DANIEL YIP |
| Issued | 11/6/2024 | APPLICANT |
| CofO in Progress | 2/3/2026 | ASHLEY THOMPSON |
| Permit Finaled | 2/4/2026 | RICHARD STEINBACH |
| CofO Issued | 2/4/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/4/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 9/21/2024 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 10/16/2024 | DANIEL YIP |
Contact Information
| Architect | Brumer,, Aaron Jason; Lic. No.: NA30005 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/18/2025 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Barrier | 3/18/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 3/18/2025 | Approved | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 3/19/2025 | Partial Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 4/10/2025 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 6/10/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 6/10/2025 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 6/16/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 6/20/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 6/24/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 6/24/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 6/24/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 6/27/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 6/27/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 6/27/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 6/27/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | EVAN COOPER |
| Green Building Rough | 7/17/2025 | Approved | EVAN COOPER |
| Insulation | 7/24/2025 | Partial Approval | MEL KHACHATOURIAN |
| Rough-Elec/Plmb/HVAC | 7/25/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 7/31/2025 | Approved | EVAN COOPER |
| Insulation | 7/31/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/19/2025 | Partial Approval | ASHLEY THOMPSON |
| Special/Order Compliance | 8/19/2025 | Partial Inspection | ARAM AVEDISIAN |
| Underground Mechanical | 9/15/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 1/21/2026 | Corrections Issued | ASHLEY THOMPSON |
| Final | 1/21/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 1/21/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 1/21/2026 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 1/21/2026 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 1/21/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 1/28/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 1/28/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Final | 1/28/2026 | Approved | ASHLEY THOMPSON |
| Smoke Detectors | 1/28/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 2/2/2026 | Approved | ASHLEY THOMPSON |
| Final | 2/2/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| HVAC-Final | 2/2/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 2/2/2026 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 2/2/2026 | Approved | ASHLEY THOMPSON |
| Smoke Detectors | 2/2/2026 | Approved | ASHLEY THOMPSON |