1255 S SPAULDING AVE 90019

Certificate Information: 1255 S SPAULDING AVE 90019

Application / Permit
24014-10000-03460
Plan Check / Job No.
B24LA16624
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing 1 story detached garage with addtion to ADU per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 2/3/2025
Issuing Office
Metro
Current Status
CofO Issued on 9/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 AUNG SOE
Corrections Issued 8/12/2024 AUNG SOE
Building Plans Picked Up 8/16/2024 APPLICANT
Applicant returned to address corrections 11/7/2024 NEHEMIAS RAMOS
Plan Check Approved 12/13/2024 NEHEMIAS RAMOS
Issued 2/3/2025 APPLICANT
CofO in Progress 9/10/2025 ARTHUR NEGRETE
Permit Finaled 9/13/2025 DEROLD HAUFF
CofO Issued 9/13/2025 DEROLD HAUFF
Permit Finaled 9/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/31/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 10/31/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 11/4/2024 CHRISTINA BRACO
Sewer availability Cleared 11/4/2024 CHRISTINA BRACO

Contact Information

Contractor Toss Guillen Erick; Lic. No.: 1080011-B 152 E 102ND STREET      LOS ANGELES, CA 90003

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2025 Partial Inspection JOSH MEISTER
Footing/Foundation/Slab 2/25/2025 Approved ARTHUR NEGRETE
METHANE-Barrier 2/25/2025 Approved ARTHUR NEGRETE
METHANE-Subgrade 2/25/2025 Approved ARTHUR NEGRETE
Underground Mechanical 2/25/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 4/1/2025 Approved ARTHUR NEGRETE
HVAC-Rough 4/1/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 4/1/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Approved ARTHUR NEGRETE
METHANE-Rough 4/4/2025 Approved ARTHUR NEGRETE
Green Building Rough 4/24/2025 Approved ARTHUR NEGRETE
Insulation 4/24/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 4/24/2025 Approved ARTHUR NEGRETE
Shower Pan 4/24/2025 Approved ARTHUR NEGRETE
Drywall Nailing 4/30/2025 Approved ARTHUR NEGRETE
Gas Test 6/2/2025 Approved ARTHUR NEGRETE
Sewer 6/5/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 7/1/2025 Approved ARTHUR NEGRETE
Final 7/1/2025 Partial Inspection ARTHUR NEGRETE
Green Building Final 7/1/2025 Partial Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 7/1/2025 Approved ARTHUR NEGRETE
Final 7/7/2025 Conditional Approval ARTHUR NEGRETE
Green Building Final 7/7/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 8/1/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 8/15/2025 Approved ARTHUR NEGRETE
Final 8/15/2025 Conditional Approval ARTHUR NEGRETE
HVAC-Final 8/15/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 8/15/2025 Approved ARTHUR NEGRETE
Final 9/9/2025 OK to Issue CofO ARTHUR NEGRETE