6322 W WARNER DR 90048
Certificate Information: 6322 W WARNER DR 90048
- Application / Permit
- 24014-10000-03451
- Plan Check / Job No.
- B24LA16479
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO CONVERT EXISTING GARAGE TO ADU PER WFPP
- Permit Issued
- Issued on 7/7/2025
- Issuing Office
- Metro
- Current Status
- Issued on 7/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2024 | JOSEPH RAFOLS |
| Corrections Issued | 8/5/2024 | JOSEPH RAFOLS |
| Building Plans Picked Up | 8/12/2024 | APPLICANT |
| Applicant returned to address corrections | 10/7/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 6/30/2025 | JOHN MESIAS |
| Issued | 7/7/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2024 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 8/24/2024 | JOSE HERNANDEZ |
| Miscellaneous | Cleared | 8/27/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 8/27/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 8/27/2024 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2024 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 9/7/2024 | JOSE HERNANDEZ |
| HPOZ | Cleared | 6/27/2025 | DEBORAH MCGILL |
| Historic monument | Cleared | 6/27/2025 | DEBORAH MCGILL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/4/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 12/3/2025 | Partial Approval | RONNIE MINDANAO |
| METHANE-Barrier | 12/3/2025 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 12/3/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 1/27/2026 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 3/23/2026 | Corrections Issued | RONNIE MINDANAO |
| Sewer | 3/23/2026 | Partial Approval | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/27/2026 | No Access for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 4/27/2026 | No Access for Inspection | RONNIE MINDANAO |
| Sewer | 4/27/2026 | No Access for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/28/2026 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 4/28/2026 | Corrections Issued | RONNIE MINDANAO |
| Gas Test | 4/30/2026 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 4/30/2026 | Approved | RONNIE MINDANAO |
| Sewer | 4/30/2026 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 5/5/2026 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 5/8/2026 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 5/15/2026 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 6/2/2026 | Corrections Issued | RONNIE MINDANAO |
| Green Building Rough | 6/2/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 6/2/2026 | Approved | RONNIE MINDANAO |