14307 W MIRANDA ST 91401

Certificate Information: 14307 W MIRANDA ST 91401

Application / Permit
24014-10000-03444
Plan Check / Job No.
B24LA16439
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE EXISTING COVERED PORCH AND INTERIOR ALTERATION TO (E) SFD
Permit Issued
Issued on 9/6/2024
Issuing Office
Metro
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2024 APPLICANT
Assigned to Plan Check Engineer 8/5/2024 NEHEMIAS RAMOS
Corrections Issued 8/6/2024 NEHEMIAS RAMOS
Building Plans Picked Up 8/9/2024 APPLICANT
Applicant returned to address corrections 8/26/2024 LAWRENCE QUIRANTE
Plan Check Approved 9/4/2024 MINA HABILI
Issued 9/6/2024 APPLICANT
CofO in Progress 12/18/2024 RYAN SALAZAR
Permit Finaled 12/24/2024 RUBEN SALAS
CofO Issued 12/24/2024 RUBEN SALAS
Permit Finaled 12/24/2024 RUBEN SALAS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Mel'S Builders & Design Inc; Lic. No.: 1025553-B 958 N WESTERN AVE APT #72      LOS ANGELES, CA 90029
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/2/2024 Conditional Approval RYAN SALAZAR
ELECTRICAL-Rough 10/15/2024 Approved RYAN SALAZAR
Footing/Foundation/Slab 10/15/2024 Approved RYAN SALAZAR
Gas Test 10/15/2024 Approved RYAN SALAZAR
HVAC-Rough 10/15/2024 Approved RYAN SALAZAR
PLUMBING-Rough 10/15/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/16/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Approved RYAN SALAZAR
Green Building Rough 10/16/2024 Approved RYAN SALAZAR
Wood Frame 10/16/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/18/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 10/21/2024 Approved JUAN VALENZUELA
Interior/Exterior Lathing 10/21/2024 Approved JUAN VALENZUELA
ELECTRICAL-Final 12/17/2024 Approved RYAN SALAZAR
Final 12/17/2024 OK to Issue CofO RYAN SALAZAR
Green Building Final 12/17/2024 Approved RYAN SALAZAR
HVAC-Final 12/17/2024 Approved RYAN SALAZAR
PLUMBING-Final 12/17/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/17/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 12/17/2024 Not Required RYAN SALAZAR
Smoke Detectors 12/17/2024 Approved RYAN SALAZAR