624 S LA BREA AVE 90036

Certificate Information: 624 S LA BREA AVE 90036

Application / Permit
24014-10000-03436
Plan Check / Job No.
B24LA16351
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
ePLAN. NEW ATTACHED COVERED OUTDOOR DINING AREA WITH RESTROOM.
Permit Issued
Issued on 1/9/2026
Issuing Office
Metro
Current Status
Issued on 1/9/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/5/2024 APPLICANT
Assigned to Zoning Architect 8/15/2024 SARHAD GHEVANDIAN
Assigned to Plan Check Engineer 8/22/2024 KEVIN MORALES
Corrections Issued 8/26/2024 KEVIN MORALES
Quality Review Completed 8/27/2024 EUGENE BARBEAU
Applicant returned to address corrections 12/4/2024 KEVIN MORALES
Applicant returned to address corrections 12/26/2024 KEVIN MORALES
Applicant returned to address corrections 1/9/2025 KEVIN MORALES
Applicant returned to address corrections 3/11/2025 KEVIN MORALES
Plan Check Approved 3/14/2025 KEVIN MORALES
Issued 1/9/2026 APPLICANT

Permit Application Clearance Information

Green Code Cleared 10/2/2024 Sai Khum
CPC Cleared 10/7/2024 MATHEW QUAN
ZA Case Cleared 10/7/2024 MATHEW QUAN
ZA Case Cleared 10/7/2024 MATHEW QUAN
Roof/Waste drainage to street Cleared 10/23/2024 AMBER CAMPBELL
DAS Clearance Cleared 12/10/2024 Sai Khum
Zoning Plan Check Cleared 2/28/2025 SARHAD GHEVANDIAN
Food establishment approval Cleared 3/11/2025 LACDHS APPROVED
Eng Process Fee Ord 176,300 Cleared 3/12/2025 AMBER CAMPBELL
Sewer availability Cleared 3/12/2025 AMBER CAMPBELL

Contact Information

Architect Cannon,, Nicole Lorraine; Lic. No.: NA31358       ,
Contractor Engine Construction Inc; Lic. No.: 1024143-B       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/23/2026 Partial Inspection CHRISTOPHER BLACKWOOD
Excavation/Setback/Form/Re-Bar 2/10/2026 Partial Approval IAN BLINN
Excavation/Setback/Form/Re-Bar 3/13/2026 Partial Approval MARTIN TAVITIAN
Footing/Foundation/Slab 3/13/2026 Partial Approval MARTIN TAVITIAN
METHANE-Barrier 3/13/2026 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Subgrade 3/13/2026 Not Ready for Inspection MARTIN TAVITIAN
Excavation/Setback/Form/Re-Bar 4/16/2026 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 4/16/2026 Partial Approval CHRISTOPHER BLACKWOOD
Floor/Roof Diaphrgm/Shear Wall 6/1/2026 Partial Approval IAN BLINN