23324 S MALTBY PL 90710
Certificate Information: 23324 S MALTBY PL 90710
- Application / Permit
- 24014-10000-03433
- Plan Check / Job No.
- B24LA16316
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 20'-6" x 9'-8" ADDITION OF A RECREATION ROOM AND LAUNDRY TO THE (E) SINGLE FAMILY DWELLING, ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/18/2025
- Issuing Office
- Current Status
- CofO Issued on 11/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/10/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 8/27/2024 | SARKIS HARABEDIAN |
| Issued | 2/18/2025 | APPLICANT |
| CofO in Progress | 11/25/2025 | EUGENE CASSIDY |
| Permit Finaled | 11/25/2025 | ANSON MAGLASANG |
| CofO Issued | 11/25/2025 | ANSON MAGLASANG |
| Permit Finaled | 11/25/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/23/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2024 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/25/2025 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 2/25/2025 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 2/25/2025 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 2/25/2025 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/5/2025 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/9/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/9/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/12/2025 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/12/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 8/12/2025 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 8/12/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/12/2025 | Approved | EUGENE CASSIDY |
| Insulation | 8/20/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/20/2025 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/29/2025 | Approved | EUGENE CASSIDY |
| Final | 10/29/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/29/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 10/29/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/24/2025 | Approved | EUGENE CASSIDY |
| Final | 11/24/2025 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 11/24/2025 | Approved | EUGENE CASSIDY |
| HVAC-Final | 11/24/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 11/24/2025 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 11/24/2025 | Approved | EUGENE CASSIDY |