1127 N PIONEER AVE 90744

Certificate Information: 1127 N PIONEER AVE 90744

Application / Permit
24014-10000-03427
Plan Check / Job No.
B24LA16275
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
COVERT (E) GARAGE WITH ADDITION TO DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) (1-STORY)
Permit Issued
Issued on 11/14/2024
Issuing Office
Current Status
CofO Issued on 5/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2024 APPLICANT
Assigned to Plan Check Engineer 8/9/2024 JOSEPH RAFOLS
Corrections Issued 8/12/2024 JOSEPH RAFOLS
Applicant returned to address corrections 9/19/2024 JOSEPH RAFOLS
Applicant returned to address corrections 10/8/2024 ALEXANDER JOO
Plan Check Approved 10/30/2024 CARLOS MONTES
Issued 11/14/2024 APPLICANT
CofO in Progress 5/2/2025 EUGENE CASSIDY
Permit Finaled 5/5/2025 ANSON MAGLASANG
CofO Issued 5/5/2025 ANSON MAGLASANG
Permit Finaled 5/5/2025 ANSON MAGLASANG

Permit Application Clearance Information

"Q" conditions Cleared 8/13/2024 DANIEL CORONADO
Clean Up Green Up Cleared 8/13/2024 DANIEL CORONADO
Address approval Cleared 8/14/2024 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 8/19/2024 KHAING AYE
Sewer availability Cleared 8/19/2024 KHAING AYE
Roof/Waste drainage to street Cleared 8/20/2024 KHAING AYE

Contact Information

Contractor J B Builders Fire Protection Inc; Lic. No.: 923970-B       ,
Contractor J B New Construction Inc; Lic. No.: 923970-B       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/11/2024 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 12/18/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 12/18/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 12/18/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 12/18/2024 Partial Approval EUGENE CASSIDY
Sewer 12/18/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/9/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 1/16/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 1/16/2025 Approved EUGENE CASSIDY
Green Building Rough 1/16/2025 Approved EUGENE CASSIDY
HVAC-Rough 1/16/2025 Approved EUGENE CASSIDY
METHANE-Rough 1/16/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 1/16/2025 Approved EUGENE CASSIDY
Insulation 1/21/2025 Approved ANSON MAGLASANG
Drywall Nailing 1/23/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 1/23/2025 Partial Approval JOSEPH MCGARRY
Shower Pan 1/23/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 1/28/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/18/2025 Corrections Issued EUGENE CASSIDY
Final 4/25/2025 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 4/25/2025 Approved EUGENE CASSIDY
Green Building Final 4/25/2025 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/25/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 4/25/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 5/2/2025 Approved EUGENE CASSIDY
Final 5/2/2025 OK to Issue CofO EUGENE CASSIDY
Green Building Final 5/2/2025 Approved EUGENE CASSIDY
HVAC-Final 5/2/2025 Approved EUGENE CASSIDY
PLUMBING-Final 5/2/2025 Approved EUGENE CASSIDY
Service/Power Release 5/2/2025 Approved EUGENE CASSIDY