17619-17621 W TULSA ST 91344

Certificate Information: 17619-17621 W TULSA ST 91344

Application / Permit
24014-10000-03416
Plan Check / Job No.
B24VN09326
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: GARAGE ADDITION AND CONVERT (E) ATTACHED ACCESSORY DWELLING UNIT TO CREATE 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED JUNIOR ACCESSORY DWELLING UNIT AND GARAGE PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 5/27/2025
Issuing Office
Current Status
Issued on 5/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/3/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 DANIEL YIP
Corrections Issued 8/1/2024 DANIEL YIP
Quality Review Completed 8/1/2024 GARO TELMI
Applicant returned to address corrections 10/1/2024 DANIEL YIP
Applicant returned to address corrections 10/29/2024 DANIEL YIP
Applicant returned to address corrections 12/2/2024 DANIEL YIP
Applicant returned to address corrections 5/7/2025 DANIEL YIP
Plan Check Approved 5/27/2025 DANIEL YIP
Issued 5/27/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/26/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/26/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/26/2024 RYAN CASTRO
ZI Cleared 5/15/2025 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/3/2025 Approved STEVEN BACK
Footing/Foundation/Slab 7/3/2025 Approved STEVEN BACK
Special/Order Compliance 7/3/2025 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Partial Approval JEFFREY PARD
Underground Mechanical 8/5/2025 No Access for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 9/29/2025 Not Ready for Inspection STEVEN BACK
Green Building Rough 9/29/2025 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 10/14/2025 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 12/8/2025 Approved STEVEN BACK
ELECTRICAL-Rough 12/8/2025 Approved STEVEN BACK
Green Building Rough 12/8/2025 Approved STEVEN BACK
Insulation 12/18/2025 Approved JUAN ALVARADO
Drywall Nailing 12/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
Drywall Nailing 12/31/2025 Approved STEVEN BACK