1630 1/2 W 54TH ST 90062
Certificate Information: 1630 1/2 W 54TH ST 90062
- Application / Permit
- 24014-10000-03410
- Plan Check / Job No.
- B24LA16054
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED TWO STORY ACCESSORY DWELLING UNIT PER ORDINANCE LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | JAD BASMA |
| Corrections Issued | 8/3/2024 | JAD BASMA |
| Quality Review Completed | 8/9/2024 | KEN GILL |
| Building Plans Picked Up | 8/13/2024 | APPLICANT |
| Plan Check Approved | 10/23/2024 | JAD BASMA |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 1/20/2026 | BARRY HACHE |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
| CofO Issued | 1/21/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 9/17/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 9/19/2024 | TREVOR QUAN |
| ZI | Cleared | 10/3/2024 | MANERI ROMAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/3/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 2/11/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 5/5/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 5/5/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 5/5/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Approved | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 5/8/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 5/9/2025 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 5/15/2025 | Approved | BARRY HACHE |
| Green Building Rough | 5/15/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 5/15/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 5/15/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Approved | MICHAEL LEWIS |
| Insulation | 5/29/2025 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/29/2025 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/30/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 5/30/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 6/3/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 9/26/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 9/26/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 10/31/2025 | Corrections Issued | BARRY HACHE |
| Final | 10/31/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 10/31/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 10/31/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Not Required | BARRY HACHE |
| Smoke Detectors | 10/31/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 12/15/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 12/15/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 12/15/2025 | Approved | BARRY HACHE |
| Final | 12/22/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 12/22/2025 | Not Ready for Inspection | BARRY HACHE |
| Service/Power Release | 12/22/2025 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 12/22/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 12/30/2025 | Corrections Issued | BARRY HACHE |
| Final | 12/30/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 12/30/2025 | Approved | BARRY HACHE |
| Smoke Detectors | 12/30/2025 | Approved | BARRY HACHE |
| Final | 1/2/2026 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Final | 1/2/2026 | Not Ready for Inspection | JOSH MEISTER |
| Service/Power Release | 1/2/2026 | Not Ready for Inspection | JOSH MEISTER |
| ELECTRICAL-Final | 1/6/2026 | Approved | BARRY HACHE |
| Final | 1/6/2026 | Corrections Issued | BARRY HACHE |
| Green Building Final | 1/6/2026 | Approved | BARRY HACHE |
| Final | 1/9/2026 | Not Ready for Inspection | BARRY HACHE |
| Service/Power Release | 1/9/2026 | Not Ready for Inspection | BARRY HACHE |
| Final | 1/15/2026 | OK for TCO | BARRY HACHE |
| Service/Power Release | 1/15/2026 | Approved | BARRY HACHE |
| Final | 1/20/2026 | OK to Issue CofO | BARRY HACHE |