540 E INDIANA AVE 1-4 90291
Certificate Information: 540 E INDIANA AVE 1-4 90291
- Application / Permit
- 24014-10000-03380
- Plan Check / Job No.
- B24LA15808
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- REMODEL TO (E) TWO STORY APARTMENT BUILDING, UNITS #2, #4, AND #5 ONLY.
- Permit Issued
- Issued on 3/27/2025
- Issuing Office
- Metro
- Current Status
- Issued on 3/27/2025
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | SERGIO GUTIERREZ |
| Assigned to Zoning Architect | 8/1/2024 | SARHAD GHEVANDIAN |
| Corrections Issued | 8/6/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/7/2024 | KEN GILL |
| Building Plans Picked Up | 8/12/2024 | APPLICANT |
| Applicant returned to address corrections | 12/9/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 3/17/2025 | SERGIO GUTIERREZ |
| Issued | 3/27/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2024 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2024 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 9/10/2024 | HISASHI KOBAYAKAWA |
| Tenant Habitability Plan | Cleared | 9/11/2024 | RICARDO BOHORQUEZ |
| Miscellaneous | Cleared | 9/13/2024 | YINGSHI HUANG |
| Miscellaneous | Cleared | 9/13/2024 | YINGSHI HUANG |
| Miscellaneous | Cleared | 9/13/2024 | YINGSHI HUANG |
| Hydrant and Access approval | Cleared | 11/25/2024 | LAVEON RIDER |
| Green Code | Cleared | 12/9/2024 | SERGIO GUTIERREZ |
| Coastal Zone | Cleared | 2/20/2025 | MAYELA VILLA |
| Specific Plan | Cleared | 2/20/2025 | MAYELA VILLA |
| Zoning Plan Check | Cleared | 2/25/2025 | SARHAD GHEVANDIAN |
| DAS Clearance | Cleared | 3/17/2025 | SERGIO GUTIERREZ |
Contact Information
| Contractor | M G Remodeling Inc; Lic. No.: 1089693-B | 9225 ALCOTT STREET LOS ANGELES, CA 90035 |
| Engineer | Davis,, Danny Thomas; Lic. No.: L7586 | 1197 E LOS ANGELES AVE #322 SIMI VALLEY, CA 93065 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/22/2025 | Conditional Approval | FARHAD DADBIN |
| Pre-Inspection | 8/6/2025 | Approved | NICK LAROCCA |
| Wood Frame | 8/11/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 8/28/2025 | Partial Approval | FARHAD DADBIN |
| Insulation | 9/9/2025 | Partial Approval | FARHAD DADBIN |
| Interior/Exterior Lathing | 9/9/2025 | Partial Approval | FARHAD DADBIN |
| Interior/Exterior Lathing | 9/15/2025 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 10/1/2025 | Approved | FARHAD DADBIN |
| Special/Order Compliance | 12/16/2025 | Partial Inspection | FARHAD DADBIN |
| Final | 2/23/2026 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Final | 2/23/2026 | Not Ready for Inspection | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Not Ready | PAUL DAVIDSON |
| Smoke Detectors | 2/23/2026 | Not Ready for Inspection | PAUL DAVIDSON |
| Final | 3/26/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 3/26/2026 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 3/26/2026 | Approved | FARHAD DADBIN |