540 E INDIANA AVE 1-4 90291

Certificate Information: 540 E INDIANA AVE 1-4 90291

Application / Permit
24014-10000-03380
Plan Check / Job No.
B24LA15808
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
REMODEL TO (E) TWO STORY APARTMENT BUILDING, UNITS #2, #4, AND #5 ONLY.
Permit Issued
Issued on 3/27/2025
Issuing Office
Metro
Current Status
Issued on 3/27/2025

Permit Application Status History

Submitted 7/30/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 SERGIO GUTIERREZ
Assigned to Zoning Architect 8/1/2024 SARHAD GHEVANDIAN
Corrections Issued 8/6/2024 SERGIO GUTIERREZ
Quality Review Completed 8/7/2024 KEN GILL
Building Plans Picked Up 8/12/2024 APPLICANT
Applicant returned to address corrections 12/9/2024 SERGIO GUTIERREZ
Plan Check Approved 3/17/2025 SERGIO GUTIERREZ
Issued 3/27/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/7/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 9/10/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/10/2024 HISASHI KOBAYAKAWA
Tenant Habitability Plan Cleared 9/11/2024 RICARDO BOHORQUEZ
Miscellaneous Cleared 9/13/2024 YINGSHI HUANG
Miscellaneous Cleared 9/13/2024 YINGSHI HUANG
Miscellaneous Cleared 9/13/2024 YINGSHI HUANG
Hydrant and Access approval Cleared 11/25/2024 LAVEON RIDER
Green Code Cleared 12/9/2024 SERGIO GUTIERREZ
Coastal Zone Cleared 2/20/2025 MAYELA VILLA
Specific Plan Cleared 2/20/2025 MAYELA VILLA
Zoning Plan Check Cleared 2/25/2025 SARHAD GHEVANDIAN
DAS Clearance Cleared 3/17/2025 SERGIO GUTIERREZ

Contact Information

Contractor M G Remodeling Inc; Lic. No.: 1089693-B 9225 ALCOTT STREET      LOS ANGELES, CA 90035
Engineer Davis,, Danny Thomas; Lic. No.: L7586 1197 E LOS ANGELES AVE   #322    SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/22/2025 Conditional Approval FARHAD DADBIN
Pre-Inspection 8/6/2025 Approved NICK LAROCCA
Wood Frame 8/11/2025 Not Ready for Inspection FARHAD DADBIN
Wood Frame 8/28/2025 Partial Approval FARHAD DADBIN
Insulation 9/9/2025 Partial Approval FARHAD DADBIN
Interior/Exterior Lathing 9/9/2025 Partial Approval FARHAD DADBIN
Interior/Exterior Lathing 9/15/2025 Partial Approval FARHAD DADBIN
Drywall Nailing 10/1/2025 Approved FARHAD DADBIN
Special/Order Compliance 12/16/2025 Partial Inspection FARHAD DADBIN
Final 2/23/2026 Not Ready for Inspection PAUL DAVIDSON
Green Building Final 2/23/2026 Not Ready for Inspection PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 2/23/2026 SGSOV Not Ready PAUL DAVIDSON
Smoke Detectors 2/23/2026 Not Ready for Inspection PAUL DAVIDSON
Final 3/26/2026 Not Ready for Inspection FARHAD DADBIN
Green Building Final 3/26/2026 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Approved FARHAD DADBIN
Smoke Detectors 3/26/2026 Approved FARHAD DADBIN