851 E PALMS BLVD 90291
Certificate Information: 851 E PALMS BLVD 90291
- Application / Permit
- 24014-10000-03369
- Plan Check / Job No.
- B24LA15692
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: REMODEL AND ADDITION TO EXISTING 1-STORY SINGLE FAMILY RESIDENCE
- Permit Issued
- Issued on 12/6/2024
- Issuing Office
- Current Status
- CofO Issued on 11/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2024 | SERGIO MUNIZ |
| Corrections Issued | 8/5/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 9/21/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/10/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/19/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 11/14/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 11/25/2024 | MOHAMMAD ESMAILI |
| Issued | 12/6/2024 | APPLICANT |
| CofO in Progress | 11/3/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 11/6/2025 | RICHARD STEINBACH |
| CofO Issued | 11/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Coastal Zone | Cleared | 10/24/2024 | MATHEW QUAN |
| Miscellaneous | Cleared | 10/24/2024 | MATHEW QUAN |
| Miscellaneous | Cleared | 10/24/2024 | MATHEW QUAN |
| Miscellaneous | Cleared | 10/24/2024 | MATHEW QUAN |
| Specific Plan | Cleared | 10/24/2024 | MATHEW QUAN |
| ZA Case | Cleared | 10/24/2024 | MATHEW QUAN |
| Specific Plan | Cleared | 11/7/2024 | FREDDY GARCIA |
Contact Information
| Contractor | Klein Construction; Lic. No.: 891079-B | 5017 MEDALIST CT OCEANSIDE, CA 92057 |
| Engineer | Behshid,, Farshid; Lic. No.: S4585 | 10866 WIMER COUNTRY ROAD SUNLAND, CA 91040 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 1/15/2025 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 1/16/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 1/17/2025 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/22/2025 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/27/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 2/27/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 2/27/2025 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 3/14/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/4/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 4/9/2025 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 4/15/2025 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/23/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 4/23/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/28/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 4/28/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/28/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 5/6/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 5/6/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Drywall Nailing | 5/9/2025 | Approved | JAYLIN GRAVITTE |
| Insulation | 5/9/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 5/9/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 5/20/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/26/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 9/26/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/26/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 9/26/2025 | Approved | JESUS RODRIGUEZ |
| Final | 10/1/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 10/1/2025 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 10/1/2025 | Approved | JESUS RODRIGUEZ |
| Final | 10/31/2025 | OK to Issue CofO | JESUS RODRIGUEZ |
| Service/Power Release | 11/5/2025 | Approved | DAVID FEILER |